Cabinet approves the Revised Cost Estimate of Punatsangchhu-II Hydroelectric Project in Bhutan
New Delhi, July 13 (IBNS) The Union Cabinet chaired by Prime Minister Narendra Modi has given its approval for Revised Cost Estimate (RCE) of Rs. 7290.62 crore for the ongoing 1020 MW Punatsangchhu-II Hydroelectric Project (HEP) in Bhutan.
The total cost escalation for the project, at this stage, is Rs.3512.82 crore, read a government statement.
The Project will provide surplus power to India and thus augment power availability in the country and would enable project works to proceed smoothly without interruption.
Support Our Journalism
We cannot do without you.. your contribution supports unbiased journalism
IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.
Support objective journalism for a small contribution.
Latest Headlines
Dr Reddy’s Lab Q4FY24 net profit up 36% YoY to Rs 1,307 cr Tue, May 07 2024
India's April oil consumption rises by 6% YoY: Oil Ministry Tue, May 07 2024
Indian airlines to carry 50 pct of international traffic by 2028, says Crisil Ratings Tue, May 07 2024
Justice Sanjay Kumar Mishra appointed as first President of GSTAT to operationalise resolution of GST disputes Mon, May 06 2024
India's services PMI shows marginal slowdown in April Mon, May 06 2024