US opposes unilateral recognition of Palestine, says 'state should be achieved via talks' | Pune car accident: Grandfather of 17-year-old accused has underworld connections, paid Chhota Rajan to kill Shiv Sena corporator, chargesheeted | Bangladesh MP killed in Kolkata, joint investigation launched | Pune teen who killed 2 techies after crashing his Porsche sent to remand home till June 5 | 'There are two versions, I expect fair probe': Arvind Kejriwal's first remarks on Swati Maliwal assault row

Rail Connectivity to Sikkim on fast-track: Railway Ministry

New Delhi: The Sivok-Rangpo rail project to connect Sikkim with the rest of India's rail network is showing perceptible progress with 58 percent of mining work completed in 14 main tunnels- 22.23 km of 38.65 km and 42 percent work completed of 13 major bridges, Ministry of Railways said Wednesday.