Fresh paper leak rocks India: Maharashtra TET postponed a day before exam, over 4 lakh aspirants affected | Pune fort murder case: Siya Goyal's brother says family would have called off marriage if she had objected | Donald Trump gets a road named after him in India, says 'Thank You!' | Fresh setback for Gautam Adani? US judge asks DoJ to justify dropping criminal charges | Ram Mandir Trust chief Champat Rai resigns as alleged donation siphoning row escalates | Ram Mandir fund row deepens: 8 arrested days after BJP called allegations 'false narrative' | 'Who tied the hands of CBI?': Calcutta HC on RG Kar case; victim's mother, now BJP MLA, says she is 'deeply disturbed' | Construction comes to a standstill at nearly 700 Kolkata projects after Taratala warehouse tragedy kills 15 | World Cup shocker! Ecuador stun Germany 2-1, storm into Round of 32 | Iran-US conflict: Cargo vessel hit near Strait of Hormuz, UN agency pauses evacuation operations
Nepal Electricity
Representational image by Fre Sonneveld on Unsplash

Winter crisis: NEA plans to light up Nepali homes with Indian energy

| @indiablooms | Sep 24, 2022, at 04:27 am

Kathmandu: The Nepal Electricity Authority is planning to buy electricity from the Indian market under a six-month contract to meet the domestic demand market for power in winter.

The step will be taken at the time as  Nepal’s run-of-river hydropower projects dwindle.

By issuing a tender notice, the state-owned power utility body said that it would buy up to 365MW from Indian power traders from December 1 this year to May 31, next year, read The Kathmandu Post report.

The NEA plans to take delivery of 300MW from the Muzaffarpur substation through the Dhalkebar-Muzaffarpur cross-border transmission line and an additional 65MW through the Tanakpur substation. The electricity will be bought round-the-clock, the notice states.

Though Nepal has been exporting electricity currently because of surplus production by the hydropower projects fed by monsoon-swollen rivers, it has to import in the winter when water levels in the rivers fall and the plants produce in the range of 30-40 percent of their installed capacity.

Currently, the total installed capacity of Nepal’s power projects stands at around 2,200MW while peak hour demand for electricity on Wednesday stood at 1866MW, according to the NEA.

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.