Netaji row: Suvendu Adhikari govt strips BJP MP Anant Maharaj of state honour | Sukhbir Badal attacked by Nihang Sikh with kirpan at Maharashtra gurdwara; assailant detained | ‘If you cannot do it, we will pass an order’: Supreme Court’s final warning to Centre on food labels | ‘Time to move on’: Bombay HC sends strong message in Vijay Mallya-bank dispute | Netaji row explodes in Bengal: Suvendu Adhikari orders police action over ‘derogatory’ posts | Kolkata's NRS Hospital nurse found dead in washroom during night shift | RG Kar rape-murder case takes fresh turn as ex-TMC MLA Nirmal Ghosh arrested over cremation probe | ‘Govt has nothing to hide’: Amit Shah says ‘ready for debate’ on NEET crackdown; Rahul Gandhi hits back, ‘not interested in lecture’ | Tata Sons leadership shock: N Chandrasekaran won’t seek reappointment as chairman after February 2027 | ISI-linked Pakistani national arrested in Bengal over 'espionage' targeting Army, BSF, Railways
Dasu Project
Image: Twitter

Pakistan: Dasu Hydropower Project to miss completion deadline

| @indiablooms | Jan 07, 2023, at 03:37 am

Islamabad: The construction of the Dasu Hydropower Project (Stage-I), which has an installed capacity of 2,160 MW, will now miss the earlier competition deadline.

Power generation from the project is now expected to take place from 2026 end.

Project management, while giving a briefing to WAPDA Chairman Lt-Gen (Retd) Sajjad Ghani during his visit to Dasu Hydropower Project, said construction work was continuing simultaneously on 12 different sites, reports The Nation.

The critical diversion system will be completed in May 2023, while electricity generation from the project will commence by the end of 2026, said a statement issued here by WAPDA.

Due to Land acquisition issues, the COVID Pandemic, and terrorism incidents which are all beyond the control of Wapda, the expected COD of the Dasu Stage-I Hydropower Project (HPP) has been pushed till FY 2026-27, said WAPDA in its bulk supply tariff petition shared with National Electric Power Regulatory Authority (NEPRA), reports The Nation.

WAPDA had requested NEPRA to allow an extension in COD of the project till 2026-27.

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.