Actor Rajpal Yadav granted interim bail in ₹9-crore cheque bounce case | Learn AI or become redundant: Microsoft India President issues stark message | India’s wholesale inflation rises to 1.81% in January as manufacturing prices surge | 'India at forefront of AI revolution': PM Modi welcomes world leaders to Delhi summit | Rs 5,000 to women ahead of Tamil Nadu polls! Vijay slams Stalin, says: ‘take the money, blow the whistle’ | Modi congratulates Tarique Rahman as BNP clinches majority in Bangladesh polls | Bangladesh Polls: Tarique Rahman-led BNP secures 'absolute majority' with 151 seats in historic comeback | BJP MP files notice to cancel Rahul Gandhi's Lok Sabha membership, seeks life-long ban | Arrested in the morning, out by evening: Tycoon’s son walks free in Lamborghini crash case | ‘Why should you denigrate a section of society?’: Supreme Court pulls up ‘Ghooskhor Pandat’ makers
Dasu Project
Image: Twitter

Pakistan: Dasu Hydropower Project to miss completion deadline

| @indiablooms | Jan 07, 2023, at 03:37 am

Islamabad: The construction of the Dasu Hydropower Project (Stage-I), which has an installed capacity of 2,160 MW, will now miss the earlier competition deadline.

Power generation from the project is now expected to take place from 2026 end.

Project management, while giving a briefing to WAPDA Chairman Lt-Gen (Retd) Sajjad Ghani during his visit to Dasu Hydropower Project, said construction work was continuing simultaneously on 12 different sites, reports The Nation.

The critical diversion system will be completed in May 2023, while electricity generation from the project will commence by the end of 2026, said a statement issued here by WAPDA.

Due to Land acquisition issues, the COVID Pandemic, and terrorism incidents which are all beyond the control of Wapda, the expected COD of the Dasu Stage-I Hydropower Project (HPP) has been pushed till FY 2026-27, said WAPDA in its bulk supply tariff petition shared with National Electric Power Regulatory Authority (NEPRA), reports The Nation.

WAPDA had requested NEPRA to allow an extension in COD of the project till 2026-27.

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.