CBI moves Supreme Court challenging Kuldeep Sengar's relief in Unnao rape case | Music under attack: Islamist mob attacks James concert with bricks, stones in Bangladesh, dozens hurt | Christmas vandalism sparks mass arrests in Raipur; Assam acts too with crackdown on 'religious intolerance' | BJP's VV Rajesh becomes Thiruvananthapuram Mayor after party topples Left's 45-year-rule in city corporation | ‘I can’t bear the pain’: Indian-origin father of three dies after 8-hour hospital wait in Canada hospital | Janhvi Kapoor, Kajal Aggarwal, Jaya Prada slam brutal lynching in Bangladesh, call out ‘selective outrage’ | Tarique Rahman returns to Bangladesh after 17 years | Shocking killing inside AMU campus: teacher shot dead during evening walk | Horror on Karnataka highway: sleeper bus bursts into flames after truck crash, 9 killed | PM Modi attends Christmas service at Delhi church, sends message of love and compassion
Dasu Project
Image: Twitter

Pakistan: Dasu Hydropower Project to miss completion deadline

| @indiablooms | Jan 07, 2023, at 03:37 am

Islamabad: The construction of the Dasu Hydropower Project (Stage-I), which has an installed capacity of 2,160 MW, will now miss the earlier competition deadline.

Power generation from the project is now expected to take place from 2026 end.

Project management, while giving a briefing to WAPDA Chairman Lt-Gen (Retd) Sajjad Ghani during his visit to Dasu Hydropower Project, said construction work was continuing simultaneously on 12 different sites, reports The Nation.

The critical diversion system will be completed in May 2023, while electricity generation from the project will commence by the end of 2026, said a statement issued here by WAPDA.

Due to Land acquisition issues, the COVID Pandemic, and terrorism incidents which are all beyond the control of Wapda, the expected COD of the Dasu Stage-I Hydropower Project (HPP) has been pushed till FY 2026-27, said WAPDA in its bulk supply tariff petition shared with National Electric Power Regulatory Authority (NEPRA), reports The Nation.

WAPDA had requested NEPRA to allow an extension in COD of the project till 2026-27.

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.