Jaishankar’s high-stakes diplomatic tour: EAM to visit UAE this week, first visit amid Middle East conflict | Passport row: Barricades outside Pawan Khera’s Hyderabad house after Himanta Biswa Sarma's warning | ‘Allow excluded voters to vote’: Mamata slams voter list freeze amid SIR row, to move Supreme Court | US, Iran agree to 2-week ceasefire deal, reopening Strait of Hormuz | ‘Prudent to wait and watch’: RBI keeps repo rate unchanged at 5.25% amid global volatility | 91 lakh voters dropped from rolls in Bengal SIR; Muslim-majority Murshidabad tops deletion list | Air India CEO Campbell Wilson quits amid losses, regulatory heat after deadly Ahmedabad crash: Report | Could be taken out in one night: Donald Trump’s chilling warning to Iran as deadline approaches | IRGC Intelligence Chief Majid Khademi killed in Israeli-US strike | Setback for Arunachal CM Pema Khandu as SC orders CBI probe into public works contracts

NHAI takes steps to speed up project execution

| | May 03, 2016, at 08:35 pm
New Delhi, May 3 (IBNS) To ensure faster execution of projects, National Highways Authority of India has delegated powers to its Regional Officers (ROs) for hiring of equipment and labourers up to Rs.10 lakhs per project, and to demolish structures that fall within the right-of-way of the project.
As some of the contracts had no provision for demolition of such structures, there would often be protracted correspondence between the contractors, Project Directors and NHAI headquarters before these could be removed, often leading to delay in execution of projects. 
 
With this delegation of power to ROs, NHAI said it will be able to make encumbrance free land available more speedily to the concessionaire/contractors as laid down under the concession agreement or contract. 
 
The Regional Officers have also been instructed to ensure measurement of such structures along with videography for record purpose, said the Ministry of Road Transport & Highwayson Tuesday
 
NHAI has recently delegated powers for construction of foot over bridges under Change of Scope upto Rs. 80 lakh and for 4 and 6 laning projects upto Rs. 1 crore respectively. 
 
Similarly, Regional Officers have been delegated the power for maintenance of highways requiring urgent repair works up to Rs. 1 crore. 
 
CGM (T) jointly with Regional Officers have also been delegated power for shifting of transmission line/electric line and water pipelines/ other utilities upto Rs 10 crores and Rs 5 crores respectively. 

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.