Tiger Shroff, not Salman Khan, was the main target, probe reveals shocking details | Dammam airport attack: Indian killed, two compatriots injured as Saudi Arabia faces fresh strikes | ‘Among others’: Macron takes swipe at Trump over France unrest, calls foreign leaders’ remarks ‘stupid’ | ‘Specific threat-related inputs’: Delhi Police blocks Diljit Dosanjh’s Delhi concert | ‘Barbaad kare alfaz mere’: Ranbir Kapoor apologises for Dussehra gaffe in Kolkata | Delhi court releases CJP's Saurav Das and Ashutosh Ranka after 7 days in custody | ‘We are seeing what is happening outside our country’: Delhi HC judge’s remark as CJP leaders Saurav Das and Ashutosh Ranka withdraw custody plea | Salman Khan was the original target? Tiger Shroff firing probe reveals shocking twist | ‘UN experts are an oxymoron’: Marco Rubio takes swipe at UN, refuses to comment on India's protests | ‘US ties with no country come at India's expense’: Marco Rubio addresses concerns over Pakistan, China
Dasu Project
Image: Twitter

Pakistan: Dasu Hydropower Project to miss completion deadline

| @indiablooms | Jan 07, 2023, at 03:37 am

Islamabad: The construction of the Dasu Hydropower Project (Stage-I), which has an installed capacity of 2,160 MW, will now miss the earlier competition deadline.

Power generation from the project is now expected to take place from 2026 end.

Project management, while giving a briefing to WAPDA Chairman Lt-Gen (Retd) Sajjad Ghani during his visit to Dasu Hydropower Project, said construction work was continuing simultaneously on 12 different sites, reports The Nation.

The critical diversion system will be completed in May 2023, while electricity generation from the project will commence by the end of 2026, said a statement issued here by WAPDA.

Due to Land acquisition issues, the COVID Pandemic, and terrorism incidents which are all beyond the control of Wapda, the expected COD of the Dasu Stage-I Hydropower Project (HPP) has been pushed till FY 2026-27, said WAPDA in its bulk supply tariff petition shared with National Electric Power Regulatory Authority (NEPRA), reports The Nation.

WAPDA had requested NEPRA to allow an extension in COD of the project till 2026-27.

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.