‘Hanuman Chalisa gave me courage’: Smit Machchhar recounts flydubai cockpit battle to PM Modi | PM Modi speaks to Flydubai pilot Smit Machchhar who foiled crash plot, praises his courage | Putin praises Modi’s ‘good ideas’ to end Ukraine war, thanks Indian PM for peace efforts | Flydubai cockpit attack: Injured Indian pilot Smit Machchhar airlifted to Abu Dhabi | India backs brave flydubai pilot Smit Machchhar, Ambassador meets family after cockpit attack | ‘Saved us from a 9/11’: PM Modi praises Captain Smit Machchhar after terrifying flydubai cockpit attack | 'India is proud': PM Modi hails Flydubai Captain Smit Machchhar as ‘hero’ after mid-air cockpit horror | ‘Too early to say’: Benjamin Netanyahu on Iran link to flydubai plane incident | ‘I didn’t wait, I ran’: Israeli dentist reveals how he saved wounded Flydubai captain during cockpit attack | Israel-bound flight lands in Saudi Arabia as pilots fight in cockpit, stabbing triggers hijack scare mid-air
China-Pakistan
Pixabay

China-Pakistan: Deadlock in commissioning of Matiari-Lahore HVDC transmission project

| @indiablooms | Feb 14, 2021, at 07:21 am

Chinese company Pak Matiari- Lahore Transmission Company (PMLTC), which completed ±660kV Matiari-Lahore HVDC Transmission Project with investment of $2.2 billion in two years time, has threatened to move the international arbitration court against Pakistan government -owned company National Transmission Dispatch Company (NTDC), stating that it is creating hurdles in the commissioning of the project, media reports said.

The Chinese company has asked the board of directors of NTDC to hold a meeting and give it an opportunity for briefing on the causes of oscillation that happened on Dec 2, 2020 during the commissioning of the system, reports The News International.

It is a major flagship project of CPEC scheduled to achieve commercial operations date (COD) on 1st of March 2021. However, due to the deadlock, the commercial operation date of the project is in jeopardy, the newspaper reports.

In a letter written on February 06, 2021 to chairman of NTDC Board Naveed Ismail, Zhang Lei, Chief Executive Officer of Pak Matiari-Lahore Transmission Company, said that PMLTC completed the project in two years time and started the system commissioning on Dec 1, 2020, reported the newspaper.

The letter also mentions that since the oscillation event occurred on Dec 2, 2020, the commissioning was suspended by NTDC for more than two months now and more than 300 engineers and technicians are sitting idle at the site, the newspaper further reported.

The crucial letter has been copied to the Federal Energy Minister, Secretary Power Division and Director General (China), China Division in the Ministry of Foreign Affairs.

NTDC MD Dr Khawaja Riffat Hasan did not respond to the questions of The News on the deadlock.

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.