'Guest of India struck in international waters': Iran furious after US submarine torpedoes IRIS Dena | Bihar's 'Susashan Babu' Nitish Kumar announces exit as CM, set for Rajya Sabha debut | ‘Baseless’: India rejects claims US used its ports to strike Iran | Defiant silence: Iran women’s team refuses anthem days after Khamenei’s death | 'You’ll find out soon': Trump hints at massive retaliation after Riyadh attack, says ‘boots on ground’ may not be needed | Iran claims Netanyahu's office targeted in 'surprise missile attacks' | India, Canada to host renewable energy summit as Modi, Carney push to deepen bilateral ties | Gold, silver surge as Middle East conflict sparks safe-haven buying | Middle East tension: Several US warplanes crash in Kuwait, says Defence Ministry | Indian defence shares jump as West Asia conflict triggers investor rush
Kolkata Metro
UNI

Railways complete challenging tunnel drive of 800m in Kolkata in spite of Covid challenges

| @indiablooms | May 17, 2021, at 02:07 am

Kolkata: The Indian Railways on Sunday said the tunneling work gets completed by Tunnel Boring Machine [TBM ] in East West Metro Corridor with the breakthrough of “Urvi“ at Bowbazar, Kolkata on May 15.

With this breakthrough the entire TBM tunneling for the Kolkata East-West Metro Project is completed.

"The stretch was difficult for tunneling work as it had century old buildings. This challenging tunnel drive of 800m has been completed successfully amidst this pandemic situation following COVID-19 protocol," read a statement issued by the Ministry of  Railways.

The Tunnel Boring Machine ‘Urvi’ which had earlier completed East Bound tunnel from Esplanade to Sealdah on 09.10.2020 was relaunched from Sealdah after necessary refurbishment and inspection on 09.01.2021 to complete the balance 800 m tunneling work in West Bound tunnel from Sealdah to Bowbazar.

This drive of tunneling has been completed and the tunnel boring machine break through at Retrieval Shaft at Bowbazar has been achieved yesterday i.e. 15.05.2021.

This TBM [Urvi] has passed below Sealdah Flyover also for which vehicular movement on the Fly over was closed for 3 days for safety reasons. After completion of this TBM drive, the tunnel boring machine ‘Urvi’ along with the other stalled TBM ‘Chandi’ will be retrieved from this retrieval shaft at Bowbazar.

Excavation of shaft after ensuring the water tightness of the shaft and the affected tunnel and retrieval of the TBMs are intricate activities which have to be done safely and hence will take time.

After completion of entire excavation, both the TBMs will be retrieved in pieces from the shaft. The RCC flooring and roofing for the shaft area will be completed thereafter and the shaft top will be backfilled to prepare the ground for overground construction.

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.