‘Worst is over,’ says IndiGo CEO after flight chaos; staff told to ignore speculation | Chaos at Hyderabad's Lulu Mall! Nidhhi Agerwal swarmed by fans, police register case | TCS bets big on AI, shares spike as company reveals ambitious plan | Delhi goes into emergency mode! Work from home, vehicle bans as AQI hits ‘severe’ | Massive fire guts shanties near Eco Park in Kolkata; no casualties | Indian Visa Application Centre in Dhaka shuts down early amid rising security concerns | Market update: Sensex tumbles 120 points, Nifty below 25,850 at closing bell | ‘Won’t apologise’: Prithviraj Chavan stands firm on controversial Operation Sindoor remark despite backlash | India summons Bangladesh High Commissioner after provocative 'seven sisters' remark | Amazon eyes $10 billion investment in OpenAI — a gamechanger for AI industry!
Srinagar-SemiRingRoad

Div Com focuses on utility shifting on Srinagar Semi Ring Road

| @indiablooms | Feb 04, 2022, at 12:13 am

Srinagar/IBNS: The Divisional Commissioner (Div Com) Kashmir Pandurang K Pole Wednesday chaired a meeting focusing on utility shifting of Power Transmission on Srinagar Semi Ring Road (SRR).

The meeting deliberated over the responsibility of utility shifting on Srinagar Semi Ring Road.

The responsibility of utility shifting is included in the scope of tender and is to be carried out by the concerned contractor, official sources said.

Further, 23 power transmission towers falling under SRR in Budgam are to be relocated, while two towers in Srinagar, three Towers in Pulwama are also to be relocated, they said.

Moreover, utilities of Irrigation and Flood Control, PHE and PWD which need to be shifted due to SRR were also discussed.

On the occasion, Div Com directed concerned officers to share the KMZ file of utilities with the executing agency so that the identification of spots becomes easy for the contractor to shift the utilities.

He also directed DC Budgam to initiate the process of land acquisition soon after the spots were identified for shifting power towers.

Project Manager NHAI was also ordered to take due care to maintain the course of canals, flood channels, and network of drainage systems so that flood situations do not emerge during summers in future.

He also directed him to construct bridges at various locations on roads being  constructed from Qazigund to Pulwama to avoid inundation by rain water. Div  Com directed him to ensure that past mistakes are not repeated which led to the  flooding in 2014 and meticulously execute the project with concerned  departments.

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.