India-US trade deal at risk? Trump imposes massive 126% duty on solar imports | ‘My life reflects this reality’: Shooter Tara Shahdeo recalls forced conversion amid Kerala Story 2 row | Modi begins Israel visit to boost defence, tech and strategic ties | Trump claims Pakistan PM told him he prevented 35 million deaths by stopping India-Pakistan conflict | Supreme Court's big move over Bengal SIR! Odisha, Jharkhand judicial officers allowed to complete revision process | ‘Kerala lives in harmony, film’s portrayal wrong’: Kerala High Court raps Kerala Story sequel makers | AI panic hits IT giants: Infosys, TCS, Wipro lead massive market rout as stocks sink to alarming lows | ‘No systemic risk’: Sanjay Malhotra breaks silence on ₹590 crore IDFC First Bank Limited fraud | India urges all nationals to leave Iran 'by available means' as US-Iran tension grows | India shines at BAFTA! All you need to know about Manipuri film Boong that stunned global cinema
Sunni Dam
Representational Image (Credit: Prateek Srivastava via Unsplash)

Cabinet grants investment approval for 382 MW Sunni Dam Hydro Electric Project in Himachal Pradesh by SJVN Ltd

| @indiablooms | Jan 05, 2023, at 02:41 am

New Delhi/IBNS: The Cabinet Committee on Economic Affairs (CCAE) Wednesday approved the investment for the 382 MW Sunni Dam Hydro Electric Project in Himachal Pradesh by SJVN Ltd.

The estimated cost of the project is Rs. 2614.51 crore including Rs 13.80 crore as budgetary support from the government for the cost of enabling infrastructure.

Ex-post facto approval is given for cumulative expenditure incurred amounting to Rs 246 crore till January 2022.

The project cost includes hard costs amounting to Rs.2246.40 crore, Interest During Construction (IDC), and Financing Charges (FC) of Rs. 358.96 crore and 9.15 crore respectively.

The revised cost sanctions for cost variations due to quantity changes (including additions/ alterations/ extra items) and time overruns due to the developer is capped at 10 percent of the sanctioned cost.

The implementation of the project is expected to generate around 4000 direct and indirect employment during the peak construction of the project.

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.