SIR row: Supreme Court to hear plea against CEC Gyanesh Kumar next week | Sambhal violence case: SC quashes key accused Mulla Afroz's NSA detention, slaps Rs 10 lakh cost on UP govt | Nandigram bypoll twist: Calcutta HC grants interim bail to Congress candidate Milan Pradhan till Oct 21 | Myanmar military airstrike horror: 49 killed, 58 injured as bombs hit crowded Rakhine market | Britain reopens refugee routes for Afghans, Palestinians as immigration and integration battle intensifies | New York Times executive shot dead: Elderly in-laws arrested amid bitter family feud over his 'trans' identity | Vijay's TVK makes Bengal entry: First party office opens in Purba Bardhaman amid state's political shake-up | SRFTI clash erupts over ABGP event: Students allege assault; BJP calls it ‘ugly face of Leftists’ | 'Asif bhai gun nikal': 17-year-old's chilling account of men posing as cops raping her in South Delhi park | Indian passport rules changed: New validity, fees for children and adults explained
Sunni Dam
Representational Image (Credit: Prateek Srivastava via Unsplash)

Cabinet grants investment approval for 382 MW Sunni Dam Hydro Electric Project in Himachal Pradesh by SJVN Ltd

| @indiablooms | Jan 05, 2023, at 02:41 am

New Delhi/IBNS: The Cabinet Committee on Economic Affairs (CCAE) Wednesday approved the investment for the 382 MW Sunni Dam Hydro Electric Project in Himachal Pradesh by SJVN Ltd.

The estimated cost of the project is Rs. 2614.51 crore including Rs 13.80 crore as budgetary support from the government for the cost of enabling infrastructure.

Ex-post facto approval is given for cumulative expenditure incurred amounting to Rs 246 crore till January 2022.

The project cost includes hard costs amounting to Rs.2246.40 crore, Interest During Construction (IDC), and Financing Charges (FC) of Rs. 358.96 crore and 9.15 crore respectively.

The revised cost sanctions for cost variations due to quantity changes (including additions/ alterations/ extra items) and time overruns due to the developer is capped at 10 percent of the sanctioned cost.

The implementation of the project is expected to generate around 4000 direct and indirect employment during the peak construction of the project.

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.