Goa nightclub fire horror: Luthra brothers brought back to India from Thailand, arrested | Messi chaos costs minister his job: Aroop Biswas resigns after Salt Lake Stadium fiasco | Bengal SIR draft list out: Around 58 lakh voters’ names dropped | Relief for Sonia, Rahul Gandhi as Delhi court refuses to act on ED chargesheet in National Herald case | Centre moves to replace MGNREGA with 'G Ram G', sets stage for winter session showdown | Messi surrounded by VIPs, fans rage: Five held in stadium vandalism case | 'Messi was uncomfortable, lost his cool!': Ex-India footballer reveals what really happened at chaotic Kolkata stadium | PM Modi embarks on historic three-nation visit to Jordan, Ethiopia, and Oman | Caught in Thailand! Fugitive Goa nightclub owners detained after deadly fire kills 25 | After Putin’s blockbuster Delhi visit, Modi set to host German Chancellor Friedrich Merz in January
Hollongi Airport

Arunachal Pradesh: Hollongi Airport to be operational soon

| @indiablooms | Oct 20, 2022, at 12:04 am

Guwahati: Construction of a New Integrated Terminal Building (NITB) with Technical Block cum Air Traffic Control tower and Apron Linked Taxiway and Associated City side works will be taken up at Imphal International Airport, Manipur.

Addressing the media, Sanmukh Jugani, Regional Executive Director, Airports Authority of India said that a new airport terminal building will be constructed with all modern facilities at Imphal International airport. Work has already been awarded and it is expected to be completed in 24 months.

The cost of the project is Rs. 500 Cr (approx) and the new terminal building will be spread in an area of 22,000 Sqm.  Which will have world class passenger facilities.

The NITB will be able to cater to around 800 passengers during Peak Hour flight operations.

            

The Annual passenger capacity of this NITB will be around 2.5 million Passengers Per Annum

The ATC Control Tower Cum Technical Block will have Ground floor + 6 floors that will be of 40-meter height.

The Service Building of the airport will be built in an Area of 2152 Sqm.

A new Apron and Taxiways will also be built with total number of eight Stands for Code –C type aircrafts- Airbus A 320 and Boeing 737.   

The Cargo complex at the Imphal Airport is being built at a Cost of Rs.16 Crore (approx.) of which physical progress of over 69 % has been completed and is expected to be completed by 31/03/2023.

The cargo complex will have a capacity of 1,05,120 MT/Annum. 

The present Terminal Building at Imphal Airport caters to around 250 arrival + 250 Departures during peak hours. It is designed for passenger handling capacity of 0.6 million Per Annum.

(Reporting by Hemanta Kumar Nath)

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.