February 05, 2026 12:52 pm (IST)
Follow us:
facebook-white sharing button
twitter-white sharing button
instagram-white sharing button
youtube-white sharing button
‘Justice crying behind closed doors’: Mamata Banerjee slams ECI in Supreme Court, CJI Kant assures solution | Mummy, Papa, sorry: Three sisters jump to death after parents object to online gaming | Supreme Court raps Meta, WhatsApp: ‘Theft of private information, won’t allow its use’ | ‘Completely surrendered’: Congress slams Modi after Trump’s trade deal move | PM Modi thanks 'dear friend' Trump for tariff reduction, hails strong US–India partnership | Trump announces US–India trade deal, lowers reciprocal tariffs to 18% | After Budget mayhem, bulls return: Sensex, Nifty stage sharp recovery | Dalai Lama wins first Grammy at 90 | Firing outside Rohit Shetty’s Mumbai home: 4 arrested, Bishnoi Gang link emerges | Female suicide attackers emerge at centre of deadly BLA assaults that rocked Pakistan’s Balochistan

BHEL commissions 500 MW Thermal Unit in Tamil Nadu

| | Jul 10, 2015, at 10:09 pm
Chennai, July 10 (IBNS) Continuing the commissioning trend in the last quarter of FY 2014-15, Bharat Heavy Electricals Limited (BHEL) on Friday said it has successfully commissioned the second 500 MW unit at Tuticorin Thermal Power Station (TPS).

The first 500 MW unit of the project was commissioned by BHEL on Friday

Tuticorin TPS has been set up by NLC Tamil Nadu Power Limited (NTPL), a joint venture of Neyveli Lignite Corporation (NLC) and Tamil Nadu Generation and Distribution Corporation (TANGEDCO). 

Earlier stages of Tuticorin TPS comprise five units of 210 MW, all installed by BHEL in three phases between 1979 and 1992. 

The BTG, Civil and BoP order for two 500 MW sets was placed on BHEL by NTPL reflecting the customer’s confidence in the company’s technological excellence and capabilities in executing such projects. 

Recently, BHEL had commissioned second unit of NLC’s 250 MW circulating fluidized bed combustion (CFBC) based power plant at Neyveli. The other project being executed by BHEL for NLC is the prestigious, 2x500 MW pulverized lignite fired thermal power plant, also coming up at Neyveli, which is the highest rating set of its kind in the country. 

Notably, BHEL commissioned 8,230 MW in the power sector utility segment in the country during the financial year 2014-15, surpassing Govt. of India’s capacity addition target of 6,914 MW set for BHEL, by 19%. 

"In all, BHELcommissioned/synchronized 11,941 MW in domestic and international markets during 2014-15, besides making major contribution to another 1600 MW by commissioning two boilers of 800 MW each. Significantly, BHEL’s installed capacity has crossed 155 GW, including 132 GW of domestic utility sets and the company has joined the elite club of international manufacturers that have supplied power generating equipment of more than 150 GW.BHEL-make 500 MW sets of this rating class today form the backbone of the Indian power sector and have been performing much above the national average as well as international benchmarks," read the company's website.

BHEL has already established its engineering prowess in the past through successfully delivering higher-rated units such as 600 MW, 660 MW and 800 MW thermal sets, having a high degree of indigenization.

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.
Related Videos
RBI announces repo rate cut Jun 06, 2025, at 10:51 am
FM Nirmala Sitharaman presents Budget 2025 Feb 01, 2025, at 03:45 pm
Nirmala Sitharaman on Budget 2024 Jul 23, 2024, at 09:30 pm