Jamia shifts classes online after clash over demand for student union polls; Congress MPs face allegations | Deadly mid-air collision: Four pilots killed as two military aircraft crash in Philippines | ‘Jihad’ calls, Modi assassination remarks: Mumbai Rapido driver arrested over alleged Jaish links | Vegetarian-only kitchen at Keralam Lok Bhavan? Governor's reported order triggers political backlash | ‘Another little Epic Fury’: Trump’s chilling warning to Iran as fresh US strikes loom | Bomb threat email names Amitabh Bachchan’s Jalsa bungalow, Diljit Dosanjh’s concert venue: Reports | ‘Face-offs still continue’: ITBP chief reveals fresh India-China border tensions in Arunachal | Eiffel Tower women staff row: BAPS monk blames ‘miscommunication’, denies delegation's role | ‘Pen, not stones and guns’: RSS-linked group opens its first office in Kashmir Valley under Muslim leader | First human case of Shamonda virus reported in France; WHO confirms death of immunocompromised patient

BHEL commissions 40 MW Hydro Power Plant in West Bengal

| | Mar 28, 2016, at 11:50 pm
Kolkata, Mar 28 (IBNS) Just a month after the commissioning of the first 40 MW hydro electric generating unit at the Teesta Low Dam Hydro Electric Project (HEP) Stage-IV in West Bengal, Bharat Heavy Electricals Limited (BHEL) has successfully commissioned the second unit of the same rating at the project.

A run-of-the-river Greenfield project located in Darjeeling district of West Bengal, Teesta HEP is being set up by National Hydroelectric Power Corporation (NHPC), on the River Teesta.

The remaining two units of the project are also in advanced stages of execution. In west Bengal, BHEL is also executing the 3x40 MW Rammam Stage-III hydro-electric project of NTPC.

The estimated annual energy generation of 720 Million Units from the project will result in significant reduction of green-house gas emissions and will help in achieving a low carbon development path for the state as well as the nation.

The order for Electrical & Mechanical (E&M) works of four units of 40 MW each was placed on BHEL by NHPC.

BHEL’s scope of work in the project consists of design, manufacture, supply, installation and commissioning of complete E&M works including vertical shaft Kaplan Turbines.

"The equipment is supplied by BHEL units at Bhopal, Jhansi, Rudrapur, Mumbai & Bengaluru and the execution of work on site is being carried out by the company’s Power Sector Eastern Region. For NHPC, BHEL is also currently executing the 4x200 MW Parbati HEP Stage-II in Himachal Pradesh and the 3x110 MW Kishanganga HEP in Jammu and Kashmir," BHEL said in a statement.

Significantly, hydro generating sets of more than 29,000 MW of various ratings have been contracted on BHEL in India and abroad. In the country, the company has so far commissioned nearly 400 Hydro generating sets of various ratings with a cumulative capacity of around 20,000 MW.

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.