Allahabad HC directs Centre to decide on Rahul Gandhi's dual citizenship row by April 21 | Nagpur communal violence: Suspected mastermind Fahim Khan's house faces bulldozer action | Habitat Studio announces shutdown after Shinde-led Shiv Sena's vandalism over Kunal Kamra's show | Lower representation in Parliament will weaken states' political strength: Stalin at delimitation meeting | Lower representation in Parliament will weaken states' political strength: Stalin at delimitation meeting | MK Stalin hosts mega multi-state meeting on delimitation in Chennai, BJP calls it drama | Cash pile accused Justice Yashwant Varma was named in CBI's FIR for alleged corruption, SC junked it later | London: Heathrow Airport resumes operation after substation fire causes power disruption | Bangladesh interim government not planning to ban Sheikh Hasina's Awami League | Fire at Delhi HC judge's house leads to recovery of unaccounted cash, SC collegium acts
Sikkim
Image Credit: PIB

Rail Connectivity to Sikkim on fast-track: Railway Ministry

| @indiablooms | Oct 21, 2022, at 03:31 am

New Delhi: The Sivok-Rangpo rail project to connect Sikkim with the rest of India's rail network is showing perceptible progress with 58 percent of mining work completed in 14 main tunnels- 22.23 km of 38.65 km and 42 percent work completed of 13 major bridges, Ministry of Railways said Wednesday.

North Eastern Region is served by Northeast Frontier Railway consisting of eight states i.e. Assam, Arunachal Pradesh, Nagaland, Manipur, Mizoram, Tripura, Meghalaya and Sikkim.

Out of eight states of the North Eastern Region, rail network connectivity now exists in seven states.

For Sikkim, the new line project Sivok-Rangpo (44 km) was sanctioned. The foundation stone of this project was laid on 30.10.2009 by the then railway minister at Sivok (West Bengal), and at Rangpo (in Sikkim) by the then vice-president of India on the same day.

Out of the total length of 44.96 km, 38.65 km (86%) is in tunnels, 2.24 km (5%) in Bridges and 4.79 km (9%) length in open cutting/filling of station yards.

The proposed line consists of 14 tunnels with the longest tunnel of 5.30 km and the smallest tunnel covering 538 metres.

Five stations including Sivok and Rangpo are planned on the proposed railway line.

Four stations are proposed to be open crossing stations e.g., Sivok, Riyang, Melli & Rangpo, and one underground halt station e.g. Teesta Bazar.

The tunnelling which is about 86% of the total length is constructed by the latest Technique called NATM (New Austrian Tunnelling Method).

The works of this project are supervised by International Consultants so that safety and quality are ensured.

IRCON is taking all the measures so that there is minimum disturbance to the Environment and Forest.                                    

The railway ministry also tweeted a video of the project.

 

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.