'He could die in two days': Delhi HC plea seeks force-feeding of Sonam Wangchuk as fast enters Day 18 | 'Tonight's defeat is hard to take': Emmanuel Macron reacts after France crash out of World Cup, congratulates Spain | Spain cruise past France to storm into FIFA World Cup 2026 final with clinical 2-0 victory | Taslima Nasrin announces Kolkata return after 20 years to attend literary event at Rabindra Sadan | 'We must not watch one of our greatest minds be sacrificed': Zeenat Aman backs Sonam Wangchuk, urges govt to open dialogue | 'I don't want Phunsukh Wangdu to die': '3 Idiots' star Omi Vaidya's emotional appeal for Sonam Wangchuk | Middle East Crisis: Iran strikes UAE tankers in Strait of Hormuz, Indian crew member killed | Picnic turns into horror: Woman allegedly harassed, family chased for 15 km in Nashik | 'Mannat is a private property': Supreme Court clears renovation of Shah Rukh Khan's Bandra residence | Bengal CM Suvendu Adhikari backs move to stop entry to Bankra Mosque inside Kolkata airport operational area
Sikkim
Image Credit: PIB

Rail Connectivity to Sikkim on fast-track: Railway Ministry

| @indiablooms | Oct 21, 2022, at 03:31 am

New Delhi: The Sivok-Rangpo rail project to connect Sikkim with the rest of India's rail network is showing perceptible progress with 58 percent of mining work completed in 14 main tunnels- 22.23 km of 38.65 km and 42 percent work completed of 13 major bridges, Ministry of Railways said Wednesday.

North Eastern Region is served by Northeast Frontier Railway consisting of eight states i.e. Assam, Arunachal Pradesh, Nagaland, Manipur, Mizoram, Tripura, Meghalaya and Sikkim.

Out of eight states of the North Eastern Region, rail network connectivity now exists in seven states.

For Sikkim, the new line project Sivok-Rangpo (44 km) was sanctioned. The foundation stone of this project was laid on 30.10.2009 by the then railway minister at Sivok (West Bengal), and at Rangpo (in Sikkim) by the then vice-president of India on the same day.

Out of the total length of 44.96 km, 38.65 km (86%) is in tunnels, 2.24 km (5%) in Bridges and 4.79 km (9%) length in open cutting/filling of station yards.

The proposed line consists of 14 tunnels with the longest tunnel of 5.30 km and the smallest tunnel covering 538 metres.

Five stations including Sivok and Rangpo are planned on the proposed railway line.

Four stations are proposed to be open crossing stations e.g., Sivok, Riyang, Melli & Rangpo, and one underground halt station e.g. Teesta Bazar.

The tunnelling which is about 86% of the total length is constructed by the latest Technique called NATM (New Austrian Tunnelling Method).

The works of this project are supervised by International Consultants so that safety and quality are ensured.

IRCON is taking all the measures so that there is minimum disturbance to the Environment and Forest.                                    

The railway ministry also tweeted a video of the project.

 

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.