CBI moves Supreme Court challenging Kuldeep Sengar's relief in Unnao rape case | Music under attack: Islamist mob attacks James concert with bricks, stones in Bangladesh, dozens hurt | Christmas vandalism sparks mass arrests in Raipur; Assam acts too with crackdown on 'religious intolerance' | BJP's VV Rajesh becomes Thiruvananthapuram Mayor after party topples Left's 45-year-rule in city corporation | ‘I can’t bear the pain’: Indian-origin father of three dies after 8-hour hospital wait in Canada hospital | Janhvi Kapoor, Kajal Aggarwal, Jaya Prada slam brutal lynching in Bangladesh, call out ‘selective outrage’ | Tarique Rahman returns to Bangladesh after 17 years | Shocking killing inside AMU campus: teacher shot dead during evening walk | Horror on Karnataka highway: sleeper bus bursts into flames after truck crash, 9 killed | PM Modi attends Christmas service at Delhi church, sends message of love and compassion
Jammu Roads

CEO ERA sets deadline for ongoing projects in Jammu  

| @indiablooms | Dec 18, 2020, at 10:21 pm

Srinagar: Chief Executive Officer, Jammu and Kashmir Economic Reconstruction Agency (JKERA) and Jammu TawiFlood Reconstruction Project (JTFRP), Dr. Syed Abid Rasheed Shah, conducted an inspection of ongoingSidhra Surinsar Road sub project being executed by JKERA under the World Bank funded Jhelum TawiFlood Recovery Project.

The Road starts from Sidhra Junction on Jammu-Srinagar Highway and isproposed to be upgraded upto km 19th of Sidhra-Surinsar Road.

The completion of this road will augment the road infrastructure to the tourist circuit of Sidhra-SurinsarMansar. It will also connect the important religious destinations of Utterbehni and Purmandal.During the inspection the CEO passed strict instructions for immediately speeding of the work andcompleting the project in the next 7 months.

Major civil works of road consist of improvement of roadgeometrics and widening of blind curves/black spots.

The CEO directed the engineering staff andcontractor to ensure that quality of the civil works is maintained as per best standards.

Engineering staff gave a detailed presentation to the CEO and apprised that the major component ofaround 60% comprises macadamisation/bituminization which will be done after the first week of March2021.The CEO directed the contractor to immediately increase the manpower and machinery deployed toensure that the project is completed well within time.

On the spot directions were issued to theEngineering staff for strict weekly monitoring of progress.Dr. Abid was accompanied by Nand Kishore Gupta Project Manager, Rajinder Kumar Sharma DeputyProject Manager and other Engineering Staff of JTFRP and consultancies along with the representativesof contractors.

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.