Vijay's TVK makes Bengal entry: First party office opens in Purba Bardhaman amid state's political shake-up | SRFTI clash erupts over ABGP event: Students allege assault; BJP calls it ‘ugly face of Leftists’ | 'Asif bhai gun nikal': 17-year-old's chilling account of men posing as cops raping her in South Delhi park | Indian passport rules changed: New validity, fees for children and adults explained | 'Terrorism by Pakistan will have consequences': India issues blunt warning at UNGA | Trouble for Gyanesh Kumar? Plea filed in Supreme Court seeking prosecution of CEC | Air India pilot suspended after failing alcohol test before Zurich-Delhi flight, weeks after marijuana case | 'Don't be selective, boycott all elections': CJP's Abhijeet Dipke's blunt message to Opposition | 'Resign by tomorrow or face nationwide protest from October 2': CJP's Abhijeet Dipke's fresh warning to Gyanesh Kumar | 'Locked' iPhone 17 at centre of mystery surrounding IIT Bombay student's death
Kashmir Railway Line

Raosaheb Patil Danve reviews progress of Katra-Banihal section of Kashmir's USBRL project

| @indiablooms | Oct 13, 2021, at 10:27 pm

Ramban/IBNS: Union Minister of State for Railways Raosaheb Patil Danve, who is on a two-day visit of district Ramban, reviewed the pace of progress on 272 kms long Udhampur-Srinagar-Baramulla railway line project besides  taking stock of issues hindering the pace of progress.

The Union Minister said there was no dearth of funds for the development and welfare of the people of the country.

Taking first hand appraisal of pace of progress on land acquisition, availability of construction material and minor minerals, the Minister directed the railway authorities, district administrations and construction agencies to redouble their efforts for timely completion which will connect the Kashmir Valley with the rest of the country through rail link.

While enquiring about causes of delay of project, the Minister also sought a detailed report on project's cost escalation from Chief Engineers of all wings of the project.

The Minister was informed that the total length of USBRL is 272 KMs, of which 161 KM has already been commissioned, and the work on the rest 111 Kms Katra-Banihal stretch is in progress and is expected to be completed by April  2023.

The Katra- Banihal stretch comprises 27 nos. of main tunnels and 8 nos. of escape tunnels which involves 97 Kms tunnelling work. The T-49 is the longest tunnel  that runs  12.75 Kms situated between Sumber-Arpinchala in Sangaldan area of the Ramban district.

The project is being constructed at an estimated cost of Rs. 27,949 crores the meeting informed, and as many as 786 people who have lost 75 percent land are provided job in Railway, besides other basic facilities being provided to the locals, the minister said.

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.