Supreme Court allows first-ever passive euthanasia for 32-year-old man in coma for 13 years | As Iran-US war disrupts global gas supply, India issues guidelines to manage shortages | LPG crisis hits metros: Commercial cylinder shortage triggers panic as govt prioritises domestic supply | Iran war disrupts LPG supplies, restaurants in major Indian cities edge towards shutdown | ‘How dare you question judicial officers?’: SC raps Bengal SIR pleas, orders appellate tribunals for voter list appeals | 'Book withdrawn': NCERT apologises for controversial judiciary chapter after Supreme Court ban | Indian stock market surges as Brent crude dips below $100 after Trump’s Iran remarks | Australia grants asylum to five Iranian women footballers after anthem protest; Albanese says ‘they are safe here’ | Trump administration labels Afghanistan ‘state sponsor of wrongful detention’ | Trump threatens Iran with ‘20 times harder’ strike if oil flow through Strait of Hormuz is disrupted
Kolkata Metro
UNI

Railways complete challenging tunnel drive of 800m in Kolkata in spite of Covid challenges

| @indiablooms | May 17, 2021, at 02:07 am

Kolkata: The Indian Railways on Sunday said the tunneling work gets completed by Tunnel Boring Machine [TBM ] in East West Metro Corridor with the breakthrough of “Urvi“ at Bowbazar, Kolkata on May 15.

With this breakthrough the entire TBM tunneling for the Kolkata East-West Metro Project is completed.

"The stretch was difficult for tunneling work as it had century old buildings. This challenging tunnel drive of 800m has been completed successfully amidst this pandemic situation following COVID-19 protocol," read a statement issued by the Ministry of  Railways.

The Tunnel Boring Machine ‘Urvi’ which had earlier completed East Bound tunnel from Esplanade to Sealdah on 09.10.2020 was relaunched from Sealdah after necessary refurbishment and inspection on 09.01.2021 to complete the balance 800 m tunneling work in West Bound tunnel from Sealdah to Bowbazar.

This drive of tunneling has been completed and the tunnel boring machine break through at Retrieval Shaft at Bowbazar has been achieved yesterday i.e. 15.05.2021.

This TBM [Urvi] has passed below Sealdah Flyover also for which vehicular movement on the Fly over was closed for 3 days for safety reasons. After completion of this TBM drive, the tunnel boring machine ‘Urvi’ along with the other stalled TBM ‘Chandi’ will be retrieved from this retrieval shaft at Bowbazar.

Excavation of shaft after ensuring the water tightness of the shaft and the affected tunnel and retrieval of the TBMs are intricate activities which have to be done safely and hence will take time.

After completion of entire excavation, both the TBMs will be retrieved in pieces from the shaft. The RCC flooring and roofing for the shaft area will be completed thereafter and the shaft top will be backfilled to prepare the ground for overground construction.

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.