Supreme Court allows first-ever passive euthanasia for 32-year-old man in coma for 13 years | As Iran-US war disrupts global gas supply, India issues guidelines to manage shortages | LPG crisis hits metros: Commercial cylinder shortage triggers panic as govt prioritises domestic supply | Iran war disrupts LPG supplies, restaurants in major Indian cities edge towards shutdown | ‘How dare you question judicial officers?’: SC raps Bengal SIR pleas, orders appellate tribunals for voter list appeals | 'Book withdrawn': NCERT apologises for controversial judiciary chapter after Supreme Court ban | Indian stock market surges as Brent crude dips below $100 after Trump’s Iran remarks | Australia grants asylum to five Iranian women footballers after anthem protest; Albanese says ‘they are safe here’ | Trump administration labels Afghanistan ‘state sponsor of wrongful detention’ | Trump threatens Iran with ‘20 times harder’ strike if oil flow through Strait of Hormuz is disrupted

Jammu-Srinagar National Highway opened today

| | Sep 16, 2014, at 04:33 pm
Udhampur, Sep 16 (IBNS): After sustained effort by the Border Road Organisation (BRO) and army engineers, the Jammu-Srinagar National Highway (NH) was opened on Tuesday, Ministry of Defence (MoD) official said.

Multiple landslides were cleared with simultaneous deployment of engineers and specialist equipment coordinated by the chief engineer of head quarter (HQ)-northern command based at Udhampur to restore the vital stretch.

Earlier, the military engineers had restored the land link to the beleaguered Kashmir Valley from the Ladakh side and cleared the Sinthan Pass route via Kishtwar.

 The major impediment to opening the NH was a massive landslide at Ramsoo near Ramban where over 300 metres of road had been entirely washed away leaving a sheer cliff of 80 degrees slope. The entire hillside had to be excavated afresh and the effort had to be further intensified due to a repeated landslide last week, a MoD press communiqué said.

Work is now on to construct a new bridge over the Ans River near Budhal which will likely to be completed in two days. Several army bridges have already been constructed and over 40 landslides cleared expeditiously by the military engineers, in an effort to improve traffic mobility on all road links across the flood-hit state.

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.