'Why can't citizens protest against the government? They are being made slaves by slapping cases': Bombay HC slams Mumbai Police, quashes activist's externment | 'First he cheats on me...': Siya Goyal's old pub video goes viral amid probe into fiancé Ketan Agarwal's alleged murder | Ronaldo's goal, Ramos' last-gasp winner send Portugal past Croatia, set up Spain clash | India-US trade deal almost done! Piyush Goyal hints at breakthrough | Ram Mandir donation scam: Champat Rai points finger at his own driver | PM Modi welcomes Japanese PM Sanae Takaichi as India-Japan ties enter a new era | 'Not an isolated incident': India slams Pakistan after 125-year-old historic Gurdwara is demolished | Ram Mandir donation theft: Six accused were employed by Varanasi-based security firm, probe reveals | Ayodhya Ram Temple donation theft: Probe says majority of money was allegedly stolen during Kumbh Mela | Commercial LPG price slashed by Rs 183.50 from July 1; check new rates in Delhi, Mumbai, Kolkata and Chennai
Kashmir

Under PMDP Jammu and Kashmir completes just 20 out of 54 projects in five years

| @indiablooms | Apr 28, 2021, at 06:46 pm

Srinagar: Five years after the announcement of Prime Minister’s Development package, Jammu and Kashmir has been able to complete just 20 projects out of 54 projects which were funded under the package.

As per the official document of the J&K’s planning department, PMDP was announced in November 2015 with 63 projects with an outlay of Rs 80,068 crore.

However post re-organization of the erstwhile state of Jammu and Kashmir into two union territories of J&K and Ladakh, nine projects with an outlay of Rs 21,441 crore were transferred to Ladakh.

UT of J&K was left with 54 projects having a budgetary allocation of 58,627 crore.

As per the official document out of 54 projects, just 20 have been completed or substantially completed, 11 have been completed and nine are substantially completed, rest of the 34 projects are still work in progress.

As per the details out of total outlay of 58,627 crore, Rs 31,721 crore were utilized.

These tobe completed projects are: Qazigund-Banihal tunnel section costing Rs 1386 crore; modernization of NIT Srinagar, Rs 100 crore; construction of government tourist assets in lieu of damaged/destroyed assets, Rs 100 crore; 12 development authorities, 3 tourist circuits, 50 tourist villages proposed under PMRP 2004, Rs 81 crore; solar off-grid home system, street lighting, Rs 37.45 crore; distribution of special assistance for augmentation of infrastructure for distribution system of power, Rs 3790 crore; support for sports infra, facilities of coaches, trainers etc, Rs 200 crore; and state government jobs to additional 3000 Kashmiri migrants, Rs 1080 crore.

Officials informed that Lt Governor has directed the Administrative Secretaries to closely monitor the execution of all PMDP projects and have a regular review of the progress made thereon in order to remove the bottlenecks, if any.

“The Lt Governor passed strict directions for speeding upon the ground implementation for early completion of the works. The Lt Governor also called for regular monitoring and submission of progress reports on a monthly basis," he said.

“Sectoral progress should be monitored regularly to avoid unnecessary delay”, he maintained.

However, according to officials, two mega projects in Kashmir – the All India Institute of Medical Sciences, and the Ring Road—announced under the PM Development Package in 2015 for Kashmir, have seen no progress since the announcement of the development package. 

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.
Related Videos
RBI announces repo rate cut Jun 06, 2025, at 10:51 am
FM Nirmala Sitharaman presents Budget 2025 Feb 01, 2025, at 03:45 pm
Nirmala Sitharaman on Budget 2024 Jul 23, 2024, at 09:30 pm