Jharkhand student protest turns tense: Water cannons, lathicharge after Assembly march barricades breached | ‘Mother tongue is as pure as one's mother’: Vijay-led Tamil Nadu government makes Tamil Thaai Vazhthu mandatory in big language push | Indian envoy Kwatra cites US, UK laws to counter ‘myths’ around FCRA Bill | Jharkhand students march to assembly today: JPSC row escalates despite govt action | ‘A morning I will cherish’: Raghav Chadha meets PM Modi, shares photos from ‘enriching’ meeting | Delhi Mercedes crash kills 70-year-old woman: Cop’s son behind wheel, beer bottle found | Indian-origin woman accused of ‘visa fraud’ on X: US Attorney steps in with major clarification | US Senate passes Russia sanctions bill: India can face Trump’s 100% tariff threat | Expired meat, rotten vegetables found at Bengaluru's luxury hotels, legal action begins | 'I'm ready to be humiliated': Vijay, Udhayanidhi Stalin clash in Tamil Nadu Assembly over Cauvery dispute
Tata Power Renewables operational capacity has reached 5.4 GW, with 4.4 GW of solar and 1 GW of wind energy projects. (Image credit: Facebook/Tata Power)

Tata Power Renewables commissions 431 MW DC solar in Madhya Pradesh’s Neemuch

| @indiablooms | Dec 03, 2024, at 11:00 pm

Mumbai: Tata Power Renewable Energy Limited (TPREL), a subsidiary of Tata Power, has successfully commissioned the 431 MW DC solar project at Neemuch in Madhya Pradesh.

Perceived to be one of India’s most cost-effective bids for large-scale solar energy production, the project was won through a competitive bidding process, the company said in a statement.

Spanning across 1,635.63 acres, the project is India’s first solar project site to incorporate cutting-edge technology, featuring a unique combination of single-axis trackers and bi-facial modules, thereby, setting a new benchmark for solar energy generation in India.

This innovative integration has boosted the efficiency of the entire system by over 15%, enabling peak power supply for extended hours.

The project is extremely innovative and was built by successfully overcoming several challenges, including rocky terrain, transmission line readiness, and remote site logistics.

Deepesh Nanda, CEO and Managing Director, Tata Power Renewable Energy Limited, said, “We are thrilled to announce the successful commissioning of the 431 MW DC solar project in Neemuch. We are confident that this project will not only reduce our carbon footprint but also strengthen our role in powering key infrastructure, including Western Central Railways and Madhya Pradesh Power Management Co. Ltd."

The project contributes to sustainability with an estimated CO2 offset of 7,80,300 tonnes and meets the highest engineering standards, with simultaneous SCADA commissioning ensuring optimal performance.

The system is CEA compliant, ensuring seamless operation of the Static Var Generator (SVG), and adheres to WRLDC compliance through the integration of harmonic filters.

This project also ensures reliable power supply to Western Central Railways and Madhya Pradesh Power Management Co. Ltd., playing a crucial role in the region's energy infrastructure.

Manu Srivastava, Additional Chief Secretary, New and Renewable Energy Department, Government of Madhya Pradesh stated, "We are pleased to partner with Tata Power Renewables on the successful commissioning of the 431 MW DC solar project. This project not only demonstrates the viability of cost-effective solar energy, with a winning bid price but also highlights the potential of sustainable energy solutions to drive India's green energy transition. By combining innovative technology and engineering excellence, we are proud to contribute to the country's renewable energy goals."

With this achievement, TPREL’s total renewable energy capacity now stands at 10.9 GW with 5.5 GW of projects in various stages of implementation, the company said.

Its operational capacity has reached 5.4 GW, comprising 4.4 GW of solar and 1 GW of wind energy projects. 

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.