Amit Shah blasts TMC over border fencing; Mamata fires back on Pahalgam and Delhi blast | 'A profound loss for Bangladesh politics': Sheikh Hasina mourns Khaleda Zia’s death | PM Modi mourns Khaleda Zia’s death, hails her role in India-Bangladesh ties | Bangladesh’s first female Prime Minister Khaleda Zia passes away at 80 | India rejects Pakistan’s Christmas vandalism remarks, cites its ‘abysmal’ minority record | Minority under fire: Hindu houses torched in Bangladesh village | Supreme Court puts Aravalli redefinition on hold amid uproar, awaits new expert committee | Supreme Court strikes! Kuldeep Sengar’s bail in Unnao case suspended amid public outcry | From bitter split to big reunion! Pawars join hands again for high-stakes civic battle | CBI moves Supreme Court challenging Kuldeep Sengar's relief in Unnao rape case
Jhelum River

Kashmir's Jhelum river carrying capacity enhanced by 25 percent from 2014

| @indiablooms | Oct 13, 2021, at 10:48 pm

Srinagar/IBNS: To prevent 2014-like floods in the Kashmir division, the carrying capacity of the river Jhelum has been enhanced by 25 percent by dredging of the river and its flood spill channels.

The 2014 devastating floods in Srinagar and its adjoining areas wreaked havoc and caused an estimated one lakh crore loss to the public and private infrastructure.

Subsequently, the Centre announced a 'Plan for Comprehensive flood management of River Jhelum and its tributaries’.

The Flood Management Plan was divided into two parts- Phase 1 and Phase 2- and so far 98 percent progress has been achieved on phase 1, while for phase 2 the J&K administration is awaiting release for funds from the Centre.

Chief Engineer of Irrigation and Flood Control Naresh Kumar said, "Carrying capacity of river Jhelum has been enhanced by 25 percent from what it was in 2014. We have done spot dredging of flood channels where the need was felt to do so.

He said, "For Phase 2 part A, investment clearance for Rs 1,623 crore has been already cleared, now we are awaiting release of funds as the Department of Water Resources have informed that funds will be released only  after they will put this project in their five year plan for 2022-26."

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.