Fresh paper leak rocks India: Maharashtra TET postponed a day before exam, over 4 lakh aspirants affected | Pune fort murder case: Siya Goyal's brother says family would have called off marriage if she had objected | Donald Trump gets a road named after him in India, says 'Thank You!' | Fresh setback for Gautam Adani? US judge asks DoJ to justify dropping criminal charges | Ram Mandir Trust chief Champat Rai resigns as alleged donation siphoning row escalates | Ram Mandir fund row deepens: 8 arrested days after BJP called allegations 'false narrative' | 'Who tied the hands of CBI?': Calcutta HC on RG Kar case; victim's mother, now BJP MLA, says she is 'deeply disturbed' | Construction comes to a standstill at nearly 700 Kolkata projects after Taratala warehouse tragedy kills 15 | World Cup shocker! Ecuador stun Germany 2-1, storm into Round of 32 | Iran-US conflict: Cargo vessel hit near Strait of Hormuz, UN agency pauses evacuation operations
Khari-Sumber Tunnel

Kashmir Rail project: Portion of Khari-Sumber tunnel completed after breakthrough

| @indiablooms | Jan 24, 2022, at 11:37 pm

Banihal/IBNS: A portion of the main tunnel under the Kashmir Rail project in the 110-kms long Banihal Katra railway track has been completed and connected Saturday at a breakthrough ceremony.

The 1,800-metres long railway tunnel between Kundan and Aarpinchala is part of the longest (about 13-kms) railway tunnel of the Indian railway and is under construction in the Khari-Sumber sector of Ramban district.

An official of IRCON International, while talking to Greater Kashmir, said the breakthrough of the main tunnel number T-49B between Kundan Adit and Aarpinchala in Khari tehsil was done successfully on Sunday.

“This part of the tunnel falls in the geological zone of Ramsoo formation which is prone to land-erosion," he said.

This formation has a Rock Mass Rating value between 15-25 and the tunnel is being constructed with the new Austrian tunneling method NATM.

“In this railway tunnel, 344M double track will be laid inside the tunnel as part of Aarpinchala yard,” he added.

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.