'Dharmendra Pradhan will be responsible if anything happens': CJP warns as Sonam Wangchuk's health worsens on day 3 of hunger strike | Adani Ports seals $1.4 billion mega deal as MSC buys 49% stake in Vizhinjam port | Ram Temple donation scam: Former trust chief Champat Rai grilled by SIT for 2 hours, says report | Brazil escape Japan scare, Germany crash out as Paraguay script World Cup shocker | India overtakes Taiwan, South Korea to become world's fifth-largest equity market again | Pakistan strikes terror hideouts near Afghan border after Karachi bloodshed, 29 killed | Israel strikes back: Top October 7 militant “eliminated” in precision operation | Radharaman Das, who defended Bengal's vegetarian mid-day meal plan, loses ISKCON post | Fresh paper leak rocks India: Maharashtra TET postponed a day before exam, over 4 lakh aspirants affected | Pune fort murder case: Siya Goyal's brother says family would have called off marriage if she had objected
Sunni Dam
Representational Image (Credit: Prateek Srivastava via Unsplash)

Cabinet grants investment approval for 382 MW Sunni Dam Hydro Electric Project in Himachal Pradesh by SJVN Ltd

| @indiablooms | Jan 05, 2023, at 02:41 am

New Delhi/IBNS: The Cabinet Committee on Economic Affairs (CCAE) Wednesday approved the investment for the 382 MW Sunni Dam Hydro Electric Project in Himachal Pradesh by SJVN Ltd.

The estimated cost of the project is Rs. 2614.51 crore including Rs 13.80 crore as budgetary support from the government for the cost of enabling infrastructure.

Ex-post facto approval is given for cumulative expenditure incurred amounting to Rs 246 crore till January 2022.

The project cost includes hard costs amounting to Rs.2246.40 crore, Interest During Construction (IDC), and Financing Charges (FC) of Rs. 358.96 crore and 9.15 crore respectively.

The revised cost sanctions for cost variations due to quantity changes (including additions/ alterations/ extra items) and time overruns due to the developer is capped at 10 percent of the sanctioned cost.

The implementation of the project is expected to generate around 4000 direct and indirect employment during the peak construction of the project.

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.