Meerut blue drum murder case: Muskaan, her lover get death sentence | 'Rise up, young patriots!': American singer Mary Millben alleges CJP gets US funding, urges peaceful protests | 'Won't go unchallenged': Muhammad Yunus heckling in New York triggers legal action warning | flydubai cockpit attack probe widens: Two Maldivian pilots detained in UAE over links to Omani co-pilot | Netflix scores big FIFA deal: All 104 World Cup 2030 matches to stream live in Spain, Andorra | Jantar Mantar crackdown: CJP's Saurav Das, Ashutosh Ranka sent to jail for 5 days | Punjab activist confronts chemist over alleged drug sales, shot dead during Facebook Live | ‘Rahul Gandhi pushed me during protest march’: Pregnant journalist’s allegation sparks BJP-Congress faceoff | ‘You cannot denotify resistance': CJP leaders Ashutosh Ranka, Saurav Das jump Jantar Mantar gate to protest, detained | Delhi Police de-notifies Jantar Mantar as protest site amid CJP stir over Gyanesh Kumar

MoU signed between MoUD and NBCC (India) Ltd, CPWD

| | Oct 26, 2016, at 02:31 am
New Delhi, Oct 25 (IBNS): A Memorandum of Understanding was signed between Ministry of Urban Development (MoUD) and National Buildings Construction Corporation (India) Ltd and Central Public Works Department (CPWD) for redevelopment of seven General Pool Residential Accommodation (GPRA) colonies in New Delhi on Tuesday.

During the occasion, the Secretary, Ministry of Urban Development, Shri Rajiv Gauba said that it is a path breaking initiative and MoUD along with NBCC and CPWD will be redeveloping the seven GPRA colonies.

He said that, earlier also, Motibagh and Kidwai Nagar (East) had been redeveloped on similar lines, but this initiative is much bigger and significant. It is self-sustainable project, he added.

The NBCC will redevelop Sarojini Nagar, Netaji Nagar, Nauroji Nagar and CPWD will redevelop Kasturba Nagar, Thyagraj Nagar, Srinivaspuri and Mohammadpur. The Union Cabinet had approved the project on 05.07.2016

The total estimated cost of the project is Rs. 32,835 crores including maintenance and operation costs for 30 years.

The cost of works assigned to NBCC would be Rs. 24,682 crores and to CPWD would be Rs. 7,793 crores.

The project shall be implemented on self-financing basis by sale of commercial Built up Area (BUA) of 8.07 lakh sqm. constructed in Nauroji Nagar and parts of Sarojini Nagar by NBCC as a part of the project.

Under the Project, the existing housing stock of 12,970, would be replaced by approx. 25,667 dwelling units, with supporting social infrastructure facilities. The construction of the project will be completed in five years, in a phased manner.

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.