Delhi erupts over lynching of Hindu man in Bangladesh; protest outside High Commission | Targeted killing sparks global outrage: American lawmakers condemn mob lynching of Hindu man in Bangladesh | Assam on a ‘powder keg’: Himanta Biswa Sarma flags demographic shift, Chicken’s Neck fears | Bangladesh on edge: Student leader shot as pre-poll violence deepens after Hadi killing | Historic deal sealed: India, New Zealand sign landmark Free Trade Agreement in record time | Supreme court snubs urgent plea to stop PMO’s chadar offering at Ajmer Sharif | Emergency landing drama: Air India flight heads back to Delhi after engine malfunction! | PM Modi slams ‘cut and commission’ TMC in virtual Taherpur address | US launches Operation Hawkeye Strike in Syria targeting ISIS after Americans killed | Horror on tracks: Rajdhani Express ploughs into elephant herd, eight killed in Assam

HCC achieves tunnel boring on crucial Delhi Metro III project

| | Jun 27, 2016, at 09:44 pm
Mumbai, June 27 (IBNS): Infrastructure major, Hindustan Construction Company (HCC) today successfully achieved a major breakthrough by day lighting the tunnel on Dwarka-Najafgarh metro corridor.

The 665-meter tunnel is part of the ambitious phase III of Delhi Metro.

The tunnel day-lighting event was witnessed by Mangu singh (MD), Shri Jitendra Tyagi (DW) and Shri Rajan Kataria (CPM).

The Tunnel Boring Machine (TBM) was launched at shaft near Sai Baba Temple and emerged out at the shaft near Hanuman Temple of Najafgarh. The same TBM will once again be deployed at the Human Temple end to dig another tunnel parallel to the tunnel completed today.

This is the third contract for underground metro being executed by HCC since October 2012 under the phase III of Delhi Metro. HCC has already completed three contracts under phase I and phase II of the Delhi Metro.

The scope of work for Package CC-66, which is underway, includes construction of 224 meter open ramp, 219 meter covered ramp  including a launching shaft, tunnel by EPBM method for 665 meter length, Cut & Cover 198 meter and station box of 288 meter. The contract also includes construction of one of the biggest underground station namely Najafgarh which is 290 meters long and 30 meters in width.


Arun Karambelkar, President and Whole Time Director, HCC Ltd, said “Overcoming all odds, the HCC project team sustained round-the-clock work to achieve this milestone. HCC has been undertaking challenging assignments in underground metro development and repeat order from DMRC reflects our ability to execute complex projects.” 

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.
Related Videos
RBI announces repo rate cut Jun 06, 2025, at 10:51 am
FM Nirmala Sitharaman presents Budget 2025 Feb 01, 2025, at 03:45 pm
Nirmala Sitharaman on Budget 2024 Jul 23, 2024, at 09:30 pm