February 14, 2026 12:09 am (IST)
Follow us:
facebook-white sharing button
twitter-white sharing button
instagram-white sharing button
youtube-white sharing button
Rs 5,000 to women ahead of Tamil Nadu polls! Vijay slams Stalin, says: ‘take the money, blow the whistle’ | Modi congratulates Tarique Rahman as BNP clinches majority in Bangladesh polls | Bangladesh Polls: Tarique Rahman-led BNP secures 'absolute majority' with 151 seats in historic comeback | BJP MP files notice to cancel Rahul Gandhi's Lok Sabha membership, seeks life-long ban | Arrested in the morning, out by evening: Tycoon’s son walks free in Lamborghini crash case | ‘Why should you denigrate a section of society?’: Supreme Court pulls up ‘Ghooskhor Pandat’ makers | Bangladesh poll manifestos mirror India’s welfare schemes as BNP, Jamaat bet big on women, freebies | Drama ends: Pakistan makes U-turn on India boycott, to play T20 World Cup clash as per schedule | ‘Won’t allow any impediment in SIR’: Supreme Court pulls up Mamata govt over delay in sharing officers’ details | India-US trade deal: ‘Negotiations always two-way’, says Amul MD amid farmers’ concerns

HCC achieves day lighting on crucial Delhi Metro III project

| | Jun 28, 2016, at 01:23 am
Mumbai, June 27 (IBNS): Infrastructure major, Hindustan Construction Company (HCC) on Monday achieved a breakthrough by day lighting the tunnel on Dwarka-Najafgarh metro corridor.
The 665-meter tunnel is part of the ambitious phase III of Delhi Metro.

The tunnel day-lighting event was witnessed by Mangu Singh (MD), Jitendra Tyagi (DW) and Rajan Kataria (CPM).

The Tunnel Boring Machine (TBM) was launched at shaft near Sai Baba Temple and emerged out at the shaft near Hanuman Temple of Najafgarh. 
 
The same TBM will once again be deployed at the Human Temple end to dig another tunnel parallel to the tunnel completed today.

This is the third contract for underground metro being executed by HCC since October 2012 under the phase III of Delhi Metro. 
 
HCC has already completed three contracts under phase I and phase II of the Delhi Metro.

The scope of work for Package CC-66, which is underway, includes construction of 224 meter open ramp, 219 meter covered ramp  including a launching shaft, tunnel by EPBM method for 665 meter length, Cut & Cover 198 meter and station box of 288 meter. 
 
The contract also includes construction of one of the biggest underground station namely Najafgarh which is 290 meters long and 30 meters in width.

Arun Karambelkar, President and Whole Time Director, HCC Ltd, said “Overcoming all odds, the HCC project team sustained round-the-clock work to achieve this milestone. HCC has been undertaking challenging assignments in underground metro development and repeat order from DMRC reflects our ability to execute complex projects.” 
 

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.
Related Videos
RBI announces repo rate cut Jun 06, 2025, at 10:51 am
FM Nirmala Sitharaman presents Budget 2025 Feb 01, 2025, at 03:45 pm
Nirmala Sitharaman on Budget 2024 Jul 23, 2024, at 09:30 pm