PM Modi slams ‘cut and commission’ TMC in virtual Taherpur address | US launches Operation Hawkeye Strike in Syria targeting ISIS after Americans killed | Horror on tracks: Rajdhani Express ploughs into elephant herd, eight killed in Assam | Horror in Bangladesh: Hindu man lynched and set on fire amid violent protests | Bangladesh in flames: Student leader Sharif Osman Hadi's death triggers massive protests, media offices torched | Chaos in Dhaka! Protesters assault New Age Editor, burn down newspaper offices amid deadly unrest | After campus shootings, Trump suspends green card lottery programme | ‘Worst is over,’ says IndiGo CEO after flight chaos; staff told to ignore speculation | Chaos at Hyderabad's Lulu Mall! Nidhhi Agerwal swarmed by fans, police register case | TCS bets big on AI, shares spike as company reveals ambitious plan

Centre is all set to start stalled works of 2000 MW Subansiri Lower Hydro project

| | Feb 13, 2017, at 09:35 pm
Guwahati, Feb 13 (IBNS): The Centre is all set to start the construction works of the stalled 2000 MW Subansiri Lower Hydro Electric Project.

A top official of the Union Power Ministry said that, the Centre is targeting to complete the works of the project by mid of 2018.

Arunachal Pradesh Chief Minister Pema Khandu on Sunday said the the Arunachal Pradesh government will sort out all the problems on implementation of the stalled hydro electric project soon.

Khandu said that, he would hold talks with the Centre and his Assam counterpart Sarbananda Sonowal into the matter for an early sorting out the issue.

Khandu and his cabinet colleagues had inspected the construction site of the hydro electric project and assured to the National Hydroelectric Power Corporation (NHPC) officials to sort out the problems for halted construction works soon.

Khandu said that, the state government losing around Rs 1.20 crore per day, which could have been accured from the 12% free power share.

Meanwhile, the top official of the Union Power Ministry said that, the stalled works of the hydro electric project will be started soon.

The construction work of the hydro electric project has been stalled since December 2011 following amid protests by anti-dam groups from Assam including Krishak Mukti Sangram Samittee (KMSS), All Assam Students Union (AASU), Asom Jatiyatabadi Yuba Chatra Parishad (AJYCP).

The anti-dam groups alleged that, the people residing in the downstream will be affected, if is any breach in the project.

The initial cost of the project was estimated at Rs 6285 crore when construction begun in 2005, and now the revised cost estimate has escalated to Rs 17,435 crore, due to delay.

On the other hand, the NHPC official said that, around 55% construction works have been completed till date.


(Reporting by Hemanta Kumar Nath)

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.
Related Videos
RBI announces repo rate cut Jun 06, 2025, at 10:51 am
FM Nirmala Sitharaman presents Budget 2025 Feb 01, 2025, at 03:45 pm
Nirmala Sitharaman on Budget 2024 Jul 23, 2024, at 09:30 pm