‘Hanuman Chalisa gave me courage’: Smit Machchhar recounts flydubai cockpit battle to PM Modi | PM Modi speaks to Flydubai pilot Smit Machchhar who foiled crash plot, praises his courage | Putin praises Modi’s ‘good ideas’ to end Ukraine war, thanks Indian PM for peace efforts | Flydubai cockpit attack: Injured Indian pilot Smit Machchhar airlifted to Abu Dhabi | India backs brave flydubai pilot Smit Machchhar, Ambassador meets family after cockpit attack | ‘Saved us from a 9/11’: PM Modi praises Captain Smit Machchhar after terrifying flydubai cockpit attack | 'India is proud': PM Modi hails Flydubai Captain Smit Machchhar as ‘hero’ after mid-air cockpit horror | ‘Too early to say’: Benjamin Netanyahu on Iran link to flydubai plane incident | ‘I didn’t wait, I ran’: Israeli dentist reveals how he saved wounded Flydubai captain during cockpit attack | Israel-bound flight lands in Saudi Arabia as pilots fight in cockpit, stabbing triggers hijack scare mid-air
BHEL
Photo Courtesy: Unsplash

BHEL bags NTPC order to set up thermal power project in Chhattisgarh

| @indiablooms | Aug 31, 2023, at 05:27 am

New Delhi: State-run engineering firm BHEL has secured the order for setting up the 2x800 MW Supercritical Thermal Power Project Stage-II at Lara in Chhattisgarh through International Competitive Bidding, according to a regulatory filing on Wednesday.

Revealing further details on the order win, the state-owned company said, “Scope of work includes Design, Engineering, Manufacture, Supply, Construction, Erection, Testing & Commissioning with Civil & Structural works for the EPC Package with Steam Generator capable of Biomass co-firing, Steam Turbine, Generator & Auxiliaries, emission control systems, control and instrumentation, balance of plant packages etc.”

According to the filing, BHEL has to execute Unit-1 within48 months from zero date and Unit-2 within 52 months from zero date.

In a separate exchange filing, NTPC communicated that its board of directors has given its nod to investment approval for setting up of Lara Super Thermal Power Project, Stage-II (2x800 MW) at Rs 15,529.99 crore.

BHEL bagged the new order days after it secured a Rs 2,242-crore order from NHPC and another worth Rs 4,000 crore from Adani Power subsidiary.

Recently, BHEL won orders amounting to Rs 4,000 crore from an Adani-group subsidiary, Mahan Energen, to supply equipment for power generation to be used in its upcoming 2x800 power project at Bandhaura, Madhya Pradesh.  Additionally, it bagged Rs 2241.86 crore worth order from NHPC Limited, Faridabad, on August 25.

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.