March 06, 2026 12:21 pm (IST)
Follow us:
facebook-white sharing button
twitter-white sharing button
instagram-white sharing button
youtube-white sharing button
'Guest of India struck in international waters': Iran furious after US submarine torpedoes IRIS Dena | Bihar's 'Susashan Babu' Nitish Kumar announces exit as CM, set for Rajya Sabha debut | ‘Baseless’: India rejects claims US used its ports to strike Iran | Defiant silence: Iran women’s team refuses anthem days after Khamenei’s death | 'You’ll find out soon': Trump hints at massive retaliation after Riyadh attack, says ‘boots on ground’ may not be needed | Iran claims Netanyahu's office targeted in 'surprise missile attacks' | India, Canada to host renewable energy summit as Modi, Carney push to deepen bilateral ties | Gold, silver surge as Middle East conflict sparks safe-haven buying | Middle East tension: Several US warplanes crash in Kuwait, says Defence Ministry | Indian defence shares jump as West Asia conflict triggers investor rush
Tunnel collapse
Image tweeted by Uttarkashi Police

Uttarakhand tunnel collapse: Rescuers to drill new tunnels for trapped workers, pipe installed to supply food

| @indiablooms | Nov 21, 2023, at 01:43 am

Silkyara/IBNS: As the 41 labourers remain trapped inside an under-construction tunnel in Uttarakhand following a wall collapse for more than a week, the agencies involved in the rescue operation are working on an alternative plan which involves tunnelling sideways and boring from the top to build a vertical shaft.

The Centre has come up with a five-option action plan that involves drilling from three sides to access the trapped workers.  Five different agencies have been tasked with carrying out each operation.

Two tunnels will be drilled horizontally from the right and left sides of the main tunnel, while a vertical shaft will be drilled from the top of the tunnel.

The labourers have been trapped in a 400-metre buffer zone of the unfinished main tunnel since November 12 when a portion of the 4.5-km tunnel on the Brahmakhal-Yamunotri National Highway collapsed, trapping 41 workers.

The tunnel -- meant to join Silkyara and Dandalgaon in Uttarkashi -- is part of the Char Dham project.

However, the big challenge is finding space for the multiple drilling machines needed in the hilly terrain and the time-consuming job of building motorable roads, which has already started.

At present, a single machine is operating in the area, clearing the way for a heavier machine. Workers are building a ramp from the main tunnel's entrance to its roof to transport the heavier machines.

On Monday morning, a wider pipe was brought and is currently being installed. This will allow rescuers to deliver a wider variety of food and medicine to the trapped people.

Earlier, only dry fruits could be sent in. With the new pipe, the authorities will be able to provide more substantial meals.

An international tunnelling expert team arrived at the spot and the International Tunnelling and Underground Space Association president Arnold Dix is overseeing the operations.

A robotics team from defence research organization DRDO has also reached.

Over the last week, several plans to cut through the 40-meter rock wall fell through.

The last rock fall took place on Friday when attempts were made to use an American Auger drill flown in from Delhi. The drill machine that was being used before that had broken down and work had to be stopped till the new one reached.

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.