‘Crash axe’ blow fractured Smit Machchhar’s skull: Shocking details emerge from flydubai cockpit horror | ‘Vote thief’ Gyanesh Kumar: Rahul Gandhi climbs barricade, waves Tricolour during explosive INDIA bloc protest | ‘Crash axe’ blow fractured Smit Machchhar’s skull: Shocking details emerge from flydubai cockpit horror | ‘He should not have been flying’: JD Vance on Flydubai co-pilot | Israel was ready to shoot down Flydubai jet if it kept flying towards Tel Aviv: Reports | 'If law wasn't followed, we can undo it': Supreme Court's big warning on SIR process amid Gyanesh Kumar row | From TMC Rajya Sabha MP to BJP nominee in 6 months: Koel Mallick's stunning political U-turn | ‘Stomp on your head’: Omani flydubai co-pilot’s chilling posts on violence against women surface | Asian Games 2026: India beat Pakistan to clinch gold in men's cricket | flydubai cockpit attack: Deleted posts expose Omani co-pilot’s views on women, alleged extremist past

Suresh Prabhu informs Assam Governor to complete Bogibeel bridge during 2017-18

| | Jul 11, 2017, at 01:36 am
Guwahati, July 10 (IBNS): Assam Governor Banwarilal Purohit who dashed off a letter to Prime Minister Narendra Modi requesting PMO’s intervention in expediting the construction of Bogibeel Bridge over the Brahmaputra in Dibrugarh district received a prompt response.

On instruction of the Prime Minister, Minister of Railways Suresh Prabhu  informed the Governor that the construction of the bridge will be completed during 2017-18.    

In a letter sent to the Governor on July 10, Union Minister Prabhu assured that the construction of the proposed Bogibeel Bridge would be completed during 2017-18 and the same can be dedicated to the service of the nation.

Following, Governor Purohit’s intense persuasion for the early commissioning of the rail-cum road Bogibell Bridge over the Brahmaputra, Prabhu mentioned that all the 42 well foundations and piers of the main bridge have been completed.

Works of both North and South guide bunds, works of rail link from Chaulkhowa to Moranhat along with connectivity on North and South Banks have also been completed.          

Presently, the work of main bridge superstructure is in progress and 35 girders out of 41 have already been launched.

Moreover deck slab concreting has commenced from north bank which is in the process on connecting the south soon.

It may be mentioned that Bogibeel Bridge is flaunted to be the longest rail-road bridge in the country and is being built at an anticipated cost of Rs 4996 crore to which an expenditure of Rs 4102 crore has already been incurred upto March 2017.

Following the perceived fact that once the bridge is completed, transportation between north and south bank of the Brahmaputra would just be a matter of time, Governor Purohit has taken special interests for the early completion of the bride.


(Reporting by Hemanta Kumar Nath)

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.