Centre imposes temporary fare caps as ticket prices defy gravity amid IndiGo meltdown | 'Action is coming': Aviation Minister blames IndiGo for countrywide air travel chaos | In front of Putin, PM Modi makes bold statement on Russia-Ukraine war: ‘India is not neutral, we side with peace!’ | Rupee weakens following RBI repo rate cut | RBI slashes repo rate by 25 basis points — big relief coming for borrowers! | 'Mamata fooled Muslims': Humayun Kabir explodes after TMC suspends him over 'Babri Masjid-style mosque' demand; announces new party | Mosque in the middle of Kolkata airport? Centre confirms flight risks, BJP fires at Mamata | Sam Altman is betting big on India! OpenAI in advanced talks with Tata to build AI infrastructure | Government removes mandatory pre-installation of Sanchar Saathi App. Know all details | Calcutta HC overturns controversial Bengal job annulment — 32,000 teachers rejoice!

Power Grid restores snowfall-hit transmission lines in J&K

| @indiablooms | Nov 05, 2018, at 09:10 pm

New Delhi, Nov 5 (IBNS): Prompt action taken by Power Grid has brought back the valley’s power to normalcy which was affected by the heavy snowfall in the late evening of Nov 3 and morning of Nov 4.

The 1600 MW normal load of power in J&K is being fulfilled in the state presently.

Heavy snowfall in areas of Jammu and Kashmir threw the normal life out of gear in the state as people suffered immensely due to power breakdown in the valley.

Both Power Grid transmission lines namely 400 kV Double Circuit New Wanpoh-Kishenpur and 400 kV Double Circuit New Wanpoh-Wagoora tripped on Sunday morning.

As soon as the fault was noticed, quick action was taken by Power Grid immediately and all Power Grid lines were restored within a span of about half an hour.

During the snowfall, three JK-PDD lines namely 132 kV Mir Bazar-Kulgam, 132 kV Mir Bazar-Lisser, 132 kV Lassipora-Shopian were also affected due to failure of towers.

The local level restoration of transmission lines is being done by JK-PDD and Power Grid jointly.

Power Grid is providing all required support along with expert manpower for quick restoration by deploying Emergency Restoration System (ERS). Power is now available in the valley and affected JK-PDD transmission lines are being restored proactively.

 

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.