Bombay HC orders CBI probe into Sushant Singh Rajput's ex-manager Disha Salian's death case | Vijay for PM in 2029? TVK says Rahul Gandhi will ‘hold his hand’ to make him Prime Minister | CJP calls off Sept 5 Delhi march after Supreme Court quashes FIRs against protesters | ‘Dismantle entire terror ecosystem’: Modi’s strong message at SCO Summit in Shehbaz’s presence | Modi’s big appeal after 7.8% GDP growth: ‘Don’t travel abroad, avoid destination weddings’ | Modi-Pezeshkian talks: Iran seeks India’s 'extensive contacts' to end West Asia war | Indus Waters Treaty row: India rejects Hague court order, says ‘no jurisdiction’ over its sovereign decisions | India beats the odds with 7.8% GDP growth; PM Modi has a message for critics | PM Modi meets Iranian President Masoud Pezeshkian during SCO summit in Kyrgyzstan | ‘Islam superior to all religions’: Karnataka minister’s remark sparks BJP-Congress war; resignation demand grows
Kolkata Metro
TBM ‘Durga’ completes key tunnel drive in Joka-Esplanade corridor. Photo: PIB/Wikimedia Commons

Kolkata Metro breakthrough: TBM ‘Durga’ completes key tunnel drive, brings Joka-Esplanade corridor closer to reality

| @indiablooms | Jul 10, 2026, at 06:56 pm

The Ministry of Railways on Friday announced a significant milestone for the Kolkata Metro, with Tunnel Boring Machine (TBM) ‘Durga’ successfully achieving a breakthrough on the Purple Line of the Joka-Esplanade Metro Corridor.

The breakthrough marks the completion of one of the underground tunnel drives between Khidderpore and Victoria, bringing the city’s ambitious metro expansion project a step closer to completion.

"The breakthrough achieved today is a key step towards strengthening Kolkata’s urban mass transit network and advancing one of the city’s most important Metro expansion projects," the Ministry said in a statement.

Key Highlights:

  • TBM ‘Durga’ successfully completed its tunnelling operation at Victoria Metro Station.
  • The breakthrough marks the completion of the Khidderpore-Victoria underground tunnel stretch, with tunnelling work having started on July 10, 2025.
  • The achievement reflects engineering excellence, precision planning and effective coordination among various stakeholders.
  • The tunnelling work was carried out while maintaining strict safety and quality standards, with minimal disruption to surface traffic.

The Joka-Esplanade Metro Corridor is expected to significantly improve east-west connectivity in Kolkata by linking the southern parts of the city with the central business district. Once operational, the corridor will provide faster, safer and more sustainable public transport, helping reduce travel time and ease road congestion.

The successful breakthrough of TBM ‘Durga’ adds to a series of major milestones achieved by Kolkata Metro in recent weeks.

Earlier, Kolkata Metro successfully bridged the critical 62-metre viaduct gap at Chingrighata on the Kavi Subhash-Airport (Orange Line) corridor, removing a major construction hurdle and paving the way for faster progress towards completion of the line.

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.