Bengal SIR progress: 47 lakh of 60 lakh adjudicated cases disposed of, Supreme Court informed | Amit Shah to join Suvendu Adhikari on Bhabanipur nomination day; BJP plans mega roadshow | Fuel prices rise: Premium petrol, diesel hiked amid oil price surge | Commercial LPG up Rs 195.50 as global oil prices rise; domestic rates unchanged | Layoff alert: Oracle cuts 30,000 jobs globally, 12,000 hit in India | ‘Unsubstantial allegations’: Calcutta HC dismisses plea on ECI’s officer transfers in Bengal | Tennis icon Leander Paes joins BJP ahead of Bengal polls | 8 killed, several injured in crowd crush at Bihar temple in Nalanda | Trump signals exit from Iran war even as Strait of Hormuz remains shut: Report | Mystery death in Pakistan: JeM chief Masood Azhar’s brother found dead
Srinagar-SemiRingRoad

Div Com focuses on utility shifting on Srinagar Semi Ring Road

| @indiablooms | Feb 04, 2022, at 12:13 am

Srinagar/IBNS: The Divisional Commissioner (Div Com) Kashmir Pandurang K Pole Wednesday chaired a meeting focusing on utility shifting of Power Transmission on Srinagar Semi Ring Road (SRR).

The meeting deliberated over the responsibility of utility shifting on Srinagar Semi Ring Road.

The responsibility of utility shifting is included in the scope of tender and is to be carried out by the concerned contractor, official sources said.

Further, 23 power transmission towers falling under SRR in Budgam are to be relocated, while two towers in Srinagar, three Towers in Pulwama are also to be relocated, they said.

Moreover, utilities of Irrigation and Flood Control, PHE and PWD which need to be shifted due to SRR were also discussed.

On the occasion, Div Com directed concerned officers to share the KMZ file of utilities with the executing agency so that the identification of spots becomes easy for the contractor to shift the utilities.

He also directed DC Budgam to initiate the process of land acquisition soon after the spots were identified for shifting power towers.

Project Manager NHAI was also ordered to take due care to maintain the course of canals, flood channels, and network of drainage systems so that flood situations do not emerge during summers in future.

He also directed him to construct bridges at various locations on roads being  constructed from Qazigund to Pulwama to avoid inundation by rain water. Div  Com directed him to ensure that past mistakes are not repeated which led to the  flooding in 2014 and meticulously execute the project with concerned  departments.

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.