July 13, 2026 03:48 am (IST)
Follow us:
facebook-white sharing button
twitter-white sharing button
instagram-white sharing button
youtube-white sharing button
'Highway blocked, stones pelted, cops injured': BJP faces open revolt in Madhya Pradesh over Narottam Mishra ticket snub | Two Kolkata Police DCPs suspended over alleged remarks against Bengal CM Suvendu Adhikari | Bail to Bloodbath: Telangana man allegedly kills wife, kids and teen who accused him of sexual harassment | Prakash Raj gets bail in multiple voter registration case linked to 2019 polls | ED raids Shekhar Suman associate's premises in FEMA case; phone allegedly thrown from 13th floor | 'Candidate fled': Prashant Kishor jibes BJP over Bankipur nominee change | BJP replaces candidate days before high-stakes Bankipur bypoll | Foreign franchise league enters India! BBL opener to be played in Chennai, announce Modi-Albanese | 'They could have stopped me': Vijay blames police, former DMK government over Karur stampede | 'People will correct their 2025 mistake': Electoral debutant Prashant Kishor predicts BJP defeat in Bankipur
Sunni Dam
Representational Image (Credit: Prateek Srivastava via Unsplash)

Cabinet grants investment approval for 382 MW Sunni Dam Hydro Electric Project in Himachal Pradesh by SJVN Ltd

| @indiablooms | Jan 05, 2023, at 02:41 am

New Delhi/IBNS: The Cabinet Committee on Economic Affairs (CCAE) Wednesday approved the investment for the 382 MW Sunni Dam Hydro Electric Project in Himachal Pradesh by SJVN Ltd.

The estimated cost of the project is Rs. 2614.51 crore including Rs 13.80 crore as budgetary support from the government for the cost of enabling infrastructure.

Ex-post facto approval is given for cumulative expenditure incurred amounting to Rs 246 crore till January 2022.

The project cost includes hard costs amounting to Rs.2246.40 crore, Interest During Construction (IDC), and Financing Charges (FC) of Rs. 358.96 crore and 9.15 crore respectively.

The revised cost sanctions for cost variations due to quantity changes (including additions/ alterations/ extra items) and time overruns due to the developer is capped at 10 percent of the sanctioned cost.

The implementation of the project is expected to generate around 4000 direct and indirect employment during the peak construction of the project.

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.