Supreme Court allows first-ever passive euthanasia for 32-year-old man in coma for 13 years | As Iran-US war disrupts global gas supply, India issues guidelines to manage shortages | LPG crisis hits metros: Commercial cylinder shortage triggers panic as govt prioritises domestic supply | Iran war disrupts LPG supplies, restaurants in major Indian cities edge towards shutdown | ‘How dare you question judicial officers?’: SC raps Bengal SIR pleas, orders appellate tribunals for voter list appeals | 'Book withdrawn': NCERT apologises for controversial judiciary chapter after Supreme Court ban | Indian stock market surges as Brent crude dips below $100 after Trump’s Iran remarks | Australia grants asylum to five Iranian women footballers after anthem protest; Albanese says ‘they are safe here’ | Trump administration labels Afghanistan ‘state sponsor of wrongful detention’ | Trump threatens Iran with ‘20 times harder’ strike if oil flow through Strait of Hormuz is disrupted
Sunni Dam
Representational Image (Credit: Prateek Srivastava via Unsplash)

Cabinet grants investment approval for 382 MW Sunni Dam Hydro Electric Project in Himachal Pradesh by SJVN Ltd

| @indiablooms | Jan 05, 2023, at 02:41 am

New Delhi/IBNS: The Cabinet Committee on Economic Affairs (CCAE) Wednesday approved the investment for the 382 MW Sunni Dam Hydro Electric Project in Himachal Pradesh by SJVN Ltd.

The estimated cost of the project is Rs. 2614.51 crore including Rs 13.80 crore as budgetary support from the government for the cost of enabling infrastructure.

Ex-post facto approval is given for cumulative expenditure incurred amounting to Rs 246 crore till January 2022.

The project cost includes hard costs amounting to Rs.2246.40 crore, Interest During Construction (IDC), and Financing Charges (FC) of Rs. 358.96 crore and 9.15 crore respectively.

The revised cost sanctions for cost variations due to quantity changes (including additions/ alterations/ extra items) and time overruns due to the developer is capped at 10 percent of the sanctioned cost.

The implementation of the project is expected to generate around 4000 direct and indirect employment during the peak construction of the project.

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.