January 20, 2025 09:17 am (IST)
Follow us:
facebook-white sharing button
twitter-white sharing button
instagram-white sharing button
youtube-white sharing button
Kolkata court convicts civic volunteer Sanjoy Roy in RG Kar rape-murder case | Saif was stabbed repeatedly, he tried to protect Taimur and Jeh: Kareena Kapoor Khan records statement with police | Escaped death by 20-25 minutes: Sheikh Hasina alleges opposition wanted to kill her | Cabinet's decision on 8th Pay Commission will improve quality of life, give boost to consumption: PM Modi | 'It has been an incredibly challenging day': Kareena Kapoor Khan requests privacy after Saif Ali Khan's stabbing incident | 'Distorting history': Mamata slams Mohan Bhagwat over his Ram Temple consecration 'marking true independence' remark | Saif Ali Khan stabbing incident: Actor who received six wounds is out of danger, one accused identified | ISRO creates history docking two Indian satellites in space | US-based short seller Hindenburg Research that targeted Adani Group and SEBI chairperson to be disbanded | Saif Ali Khan stabbed during burglary attempt at home, hospitalised; police probe on
Sunni Dam
Representational Image (Credit: Prateek Srivastava via Unsplash)

Cabinet grants investment approval for 382 MW Sunni Dam Hydro Electric Project in Himachal Pradesh by SJVN Ltd

| @indiablooms | Jan 05, 2023, at 02:41 am

New Delhi/IBNS: The Cabinet Committee on Economic Affairs (CCAE) Wednesday approved the investment for the 382 MW Sunni Dam Hydro Electric Project in Himachal Pradesh by SJVN Ltd.

The estimated cost of the project is Rs. 2614.51 crore including Rs 13.80 crore as budgetary support from the government for the cost of enabling infrastructure.

Ex-post facto approval is given for cumulative expenditure incurred amounting to Rs 246 crore till January 2022.

The project cost includes hard costs amounting to Rs.2246.40 crore, Interest During Construction (IDC), and Financing Charges (FC) of Rs. 358.96 crore and 9.15 crore respectively.

The revised cost sanctions for cost variations due to quantity changes (including additions/ alterations/ extra items) and time overruns due to the developer is capped at 10 percent of the sanctioned cost.

The implementation of the project is expected to generate around 4000 direct and indirect employment during the peak construction of the project.

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.