Christmas vandalism sparks mass arrests in Raipur; Assam acts too with crackdown on 'religious intolerance' | BJP's VV Rajesh becomes Thiruvananthapuram Mayor after party topples Left's 45-year-rule in city corporation | ‘I can’t bear the pain’: Indian-origin father of three dies after 8-hour hospital wait in Canada hospital | Janhvi Kapoor, Kajal Aggarwal, Jaya Prada slam brutal lynching in Bangladesh, call out ‘selective outrage’ | Tarique Rahman returns to Bangladesh after 17 years | Shocking killing inside AMU campus: teacher shot dead during evening walk | Horror on Karnataka highway: sleeper bus bursts into flames after truck crash, 9 killed | PM Modi attends Christmas service at Delhi church, sends message of love and compassion | Delhi erupts over lynching of Hindu man in Bangladesh; protest outside High Commission | Targeted killing sparks global outrage: American lawmakers condemn mob lynching of Hindu man in Bangladesh
Delhi Metro Rail Corportation

Cabinet approves revision in funding pattern of Delhi Metro’s three Priority Corridors of Phase – IV

| @indiablooms | Dec 11, 2019, at 11:30 pm

New Delhi/IBNS: The Union Cabinet, chaired by Prime Minister Narendra Modi, has given its approval for revision in the funding pattern of three approved priority corridors of Delhi Metro Phase-IV projects, namely, (i) Aerocity to Tughlakabad, (ii) R.K Ashram to Janakpuri (West) and (iii) Mukundpur - Maujpur with sharing of land cost in the ratio of 50:50 between Government of India (GoI) and Government of National Capital Territory of Delhi (GNCTD). 

This is in pursuance of the amendments to Metro Rail Policy, 2017 applicable only for Delhi, in compliance with the Supreme Court.

The total cost of the project which is Rs. 24,948.65 crore remains unchanged.

The contribution from GoI increases from the existing Rs. 4,154.20 crore to Rs. 4,643.638 crore resulting in a net increase of Rs. 489.438 crore.

The amount of external loan from bilateral/multilateral agencies which DMRC has to repay increases from the existing Rs. 11,462.60 crore to Rs.12,930.914 crore with a net increase of Rs. 1,468.314 crore.

Three priority corridors of Delhi Metro phase-IV project were approved by the Government of India in March, 2019 at a completion cost of Rs. 24,948.65 crore.

The funding pattern was kept in line with provisions of Metro rail policy, 2017. GNCTD in April, 2019 directed DMRC not to start work on the sanctioned corridors unless MoHUA revises the cost-sharing pattern in tune with approval concurred by them.

After intervention of the Supreme Court, the work was started in July, 2019.

The Supreme Court in its order in September, upheld the provisions of Metro Rail Policy, 2017 regarding bearing of operational losses and repayment of the external loan and currency fluctuation cost by the State in case the Special Purpose Vehicle (DMRC in this case) fails.

The Supreme Court directed to make a departure from the Policy to be applicable only in the case of Delhi and to share land cost in the ratio of 50:50 between GoI and GNCTD. The relevant para of Metro Rail Policy, 2017 is also amended accordingly.

Delhi Metro Rail Corportation


 

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.