Jharkhand student protest turns tense: Water cannons, lathicharge after Assembly march barricades breached | ‘Mother tongue is as pure as one's mother’: Vijay-led Tamil Nadu government makes Tamil Thaai Vazhthu mandatory in big language push | Indian envoy Kwatra cites US, UK laws to counter ‘myths’ around FCRA Bill | Jharkhand students march to assembly today: JPSC row escalates despite govt action | ‘A morning I will cherish’: Raghav Chadha meets PM Modi, shares photos from ‘enriching’ meeting | Delhi Mercedes crash kills 70-year-old woman: Cop’s son behind wheel, beer bottle found | Indian-origin woman accused of ‘visa fraud’ on X: US Attorney steps in with major clarification | US Senate passes Russia sanctions bill: India can face Trump’s 100% tariff threat | Expired meat, rotten vegetables found at Bengaluru's luxury hotels, legal action begins | 'I'm ready to be humiliated': Vijay, Udhayanidhi Stalin clash in Tamil Nadu Assembly over Cauvery dispute
Assam
Image Credit: The Arunachal Times

Assam: 2,000 MW Subansiri Lower Hydroelectric Project nears completion; power generation to begin by 2023-24 financial year

| @indiablooms | Jul 03, 2023, at 05:38 pm

Gerukamukh/Assam: The Subansiri Lower Hydroelectric Project (SLHEP) is nearing completion, with power generation slated to begin by the end of the 2023-24 financial year, revealed the project developer NHPC.

The construction of the dam's top level, reaching an elevation of 210 meters, has been successfully completed across all blocks as of 29th June. This accomplishment marks a significant milestone in the project's construction, as more than 90 percent of the total project works have already been finalized, reported The Arunachal Times.

The remaining work on the radial gates is scheduled to be completed after the monsoon season.

Expressing his congratulations to all the stakeholders and the entire project team, Vipin Gupta, SLP Executive Director, recognized the collaborative effort that led to this achievement.

After obtaining all the necessary statutory clearances, including forest clearance, back in October 2004, NHPC initiated the construction work in January 2005. However, the project faced a setback from December 2011 to October 2019 due to agitations and protests by local stakeholders.

Overcoming these challenges, the project obtained clearance from the National Green Tribunal, enabling the construction to recommence from October 2019.

According to the NHPC release, the construction of all major project components, including the dam, power house, and hydromechanical works, is progressing rapidly.

Once completed, the Subansiri Lower Hydroelectric Project is expected to generate approximately 7,500 million units of power annually, operating at a 90 percent dependable year. This development is set to significantly contribute to the region's power supply and further strengthen the renewable energy sector.

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.