In front of Putin, PM Modi makes bold statement on Russia-Ukraine war: ‘India is not neutral, we side with peace!’ | Rupee weakens following RBI repo rate cut | RBI slashes repo rate by 25 basis points — big relief coming for borrowers! | 'Mamata fooled Muslims': Humayun Kabir explodes after TMC suspends him over 'Babri Masjid-style mosque' demand; announces new party | Mosque in the middle of Kolkata airport? Centre confirms flight risks, BJP fires at Mamata | Sam Altman is betting big on India! OpenAI in advanced talks with Tata to build AI infrastructure | Government removes mandatory pre-installation of Sanchar Saathi App. Know all details | Calcutta HC overturns controversial Bengal job annulment — 32,000 teachers rejoice! | Bengal SIR shock: 1 lakh ‘deceased voters’ found in Kolkata North! | Massive twist in Bengal voter list: ‘Perfect’ 2,280 booths shrink to just 480 after probe!
The delay is primarily due to slow progress on three sections in Gujarat, spanning a total of 87 km. (Representational image: wikipedia.org)

Delhi-Mumbai Expressway faces two-year delay, full completion now expected by 2027: Report

| @indiablooms | Feb 20, 2025, at 09:01 pm

New Delhi: Commuters hoping to travel between Delhi and Mumbai in just 12 hours will have to wait longer, as the Delhi-Mumbai Expressway's completion has been pushed back by two years, The Times of India reported.

The delay is primarily due to slow progress on three sections in Gujarat, spanning a total of 87 km.

According to the Times of India report, one 35-km stretch has seen no progress, while two other sections have recorded only 7% and 35% completion.

The 1,382-km expressway was divided into multiple construction packages, with the initial deadline set for March 2024, later revised to October 2025.

Union Minister Nitin Gadkari recently reviewed the Rs 1 lakh crore project's progress with NHAI and ministry officials, urging expedited work.

The expressway, passing through Delhi, Haryana, Rajasthan, Madhya Pradesh, Gujarat, and Maharashtra, is expected to reduce Delhi-Mumbai travel time to 12 hours once fully operational.

Ahead of the Delhi elections, MoS for Road Transport Harsh Malhotra indicated the project would now be completed by 2026, citing land acquisition and technical challenges as key factors behind the delay.

Officials reported that Haryana’s stretch is complete, while Rajasthan’s portion is expected to be finished by March-April 2026.

"This will allow seamless travel from Delhi to Vadodara by March next year. Efforts are underway to fast-track pending work in Gujarat," an official was quoted as saying by TOI.

Most sections in Maharashtra are on track to be completed by the end of this year, except for the 21-km Jawaharlal Nehru Port link.

Initially set for MSRDC construction, the highway ministry has now approved NHAI's involvement in this segment, with cost estimates being finalised for necessary approvals.

Given standard highway construction timelines, a section typically takes two years from the start to completion.

The delayed 35-km stretch in Gujarat, awarded to a single contractor, is now projected to be ready by February 2027.

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.
Related Videos
RBI announces repo rate cut Jun 06, 2025, at 10:51 am
FM Nirmala Sitharaman presents Budget 2025 Feb 01, 2025, at 03:45 pm
Nirmala Sitharaman on Budget 2024 Jul 23, 2024, at 09:30 pm