Cabinet approves the Revised Cost Estimate of Punatsangchhu-II Hydroelectric Project in Bhutan
New Delhi, July 13 (IBNS) The Union Cabinet chaired by Prime Minister Narendra Modi has given its approval for Revised Cost Estimate (RCE) of Rs. 7290.62 crore for the ongoing 1020 MW Punatsangchhu-II Hydroelectric Project (HEP) in Bhutan.
The total cost escalation for the project, at this stage, is Rs.3512.82 crore, read a government statement.
The Project will provide surplus power to India and thus augment power availability in the country and would enable project works to proceed smoothly without interruption.
Support Our Journalism
We cannot do without you.. your contribution supports unbiased journalism
IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.
Support objective journalism for a small contribution.
Latest Headlines
TCS, Porsche join forces in major AI move to transform mobility
Tue, Aug 25 2026
Tata Power Renewables marks a major milestone with the commissioning of 190.5 MW FDRE project in Rajasthan. All details inside
Mon, Aug 24 2026
Samsung's big AI push in India: New Pune facility to power next-gen data centre cooling
Mon, Aug 24 2026
Best Indicators For Futures Trading
Mon, Aug 24 2026
China orders massive EV recall: Nearly 3 million Teslas among 4.3 million vehicles affected
Mon, Aug 24 2026
Yes Bank launches ‘YES Essence’ for women. How can you avail it?
Fri, Aug 21 2026