Caught in Thailand! Fugitive Goa nightclub owners detained after deadly fire kills 25 | After Putin’s blockbuster Delhi visit, Modi set to host German Chancellor Friedrich Merz in January | Delhi High Court slams govt, orders swift compensation as IndiGo crisis triggers fare shock and nationwide chaos | Amazon drops a massive $35 billion India bet! AI push, 1 million jobs and big plans revealed at Smbhav Summit | IndiGo’s ‘All OK’ claim falls apart! Govt slaps 10% flight cut after weeklong chaos | Centre finally aligns IndiGo flights with airline's operating ability, cuts its winter schedule by 5% | Odisha's Malkangiri in flames: Tribals rampage Bangladeshi settlers village after beheading horror! | Race against time! Indian Navy sends four more warships to Cyclone Ditwah-hit Sri Lanka | $2 billion mega deal! HD Hyundai to build shipyard in Tamil Nadu — a game changer for India | After 8 years of legal drama, Malayalam actor Dileep acquitted in 2017 rape case — what really happened?

Alstom T&D India commissions Rajasthan's first 765kV substation at Anta

| | Feb 03, 2015, at 06:51 am
New Delhi, Feb 2 (IBNS) : Alstom T&D India has successfully commissioned the Rajya Vidyut Prasaran Nigam Limited’s (RVPN) 765 kV substation in Anta.

Anta is Rajasthan’s first 765 kV substation, and the second largest with a total of twenty-six bays, ten 765 kV bays and sixteen 400 kV bays.

This substation will play a significant role in pooling and evacuating the power flow from the three major power plants in the state (Kalisindh, Kawai and Chhabra) to the national grid.

The turnkey project for Anta substation was awarded to Alstom T&D India in September 2011. 

The contract included installation of three banks of 3x500 MVA, 765/400 kV transformers, 765 kV reactors, other 765 kV equipment and civil works with a total order value of nearly €52 million (INR 4,212 million).

The Anta substation was set up by RVPN under the transmission system augmentation scheme to meet the growing energy demand in the state.

Currently, Rajasthan has an installed capacity of more than 5,000 MW, with over 3,000 MW still under construction.

Upon successful completion of this project, Rathin Basu, Country President, Alstom India & South Asia said, “The successful commissioning of the 765 kV Anta project is a major testimony in building Rajasthan’s HV and EHV grid. Despite challenging weather conditions, the Alstom and RVPN team commissioned the prestigious project in time to initiate power flow between Anta and Phagi substations. We look forward to building future HV and EHV substations to strengthen Rajasthan’s electrical grid, including potential large scale induction of renewable power.”


 

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.
Related Videos
RBI announces repo rate cut Jun 06, 2025, at 10:51 am
FM Nirmala Sitharaman presents Budget 2025 Feb 01, 2025, at 03:45 pm
Nirmala Sitharaman on Budget 2024 Jul 23, 2024, at 09:30 pm