After SC rebuke, BCI chief apologises to NALSAR students over enrolment freeze row | Independence Day: PM Modi’s big youth pitch— AI training, free coaching amid exam row and job concerns | ‘Shakti Ki Saptadhara’: Modi reveals 7 pillars to power India’s next leap in his I-Day speech from Red Fort | West Bengal STF arrests 3 more suspected Pakistani spies in Cooch Behar | Bengal man arrested in Bengaluru over terror links, Afghanistan travel plan | Ajit Doval breaks silence on Operation Sindoor in Discovery’s explosive new docuseries | Rahul Gandhi's 'mock hug' taunt sparks row; Centre stresses 'mutual respect' with Italy | Delhi on high alert: Bomb threat to High Court, airport and multiple locations ahead of I-Day | ‘Who are they to interfere?’: CJI Surya Kant slams Bar Council of India over NALSAR students’ enrolment row | 'Shows how low Congress has sunk': BJP slams Rahul Gandhi over Modi foreign policy jibe
North East

Railway connectivity towards NE gets a boost with commissioning of double line

| @indiablooms | Jul 03, 2021, at 06:43 pm

Guwahati/IBNS: CRS (Commissioner of Railway Safety) has accorded sanction for opening of Jalpaipuri Road - Y Leg section (one block section of 5 km) and Betgara - Kolaigram section (23 km in 3 block sections) double line falling on the Rajdhani route and the most busy route of N.F. Railway connecting Guwahati to rest of India.

In both these sections, double lines have been commissioned along with Railway Electrification. Completion of these doubling sections will help operation of more freight traffic to & from Northeast region.

The entire work is completed during the Covid pandemic situation by observing necessary safety protocols by the Northeast Frontier Railway.

An official of N.F. Railway said that, Jalpaiguri Road - Y Leg section was the only super critical work left to be completed in N.F. Railway.

“This section has an important bridge of 970 mt length (20 spans) on the river Teesta. This section was a bottleneck as double lines on either side of this block section already existed. Doubling on either side of Y Leg is important as this junction provides alternate route between New Jalpaiguri and New Coochbehar. Betgara - Kolaigram section is a part of New Mainaguri - Gumanihat doubling project which is a critical work of N.F. Railway,” the official said.

He further said that, this doubling being on the busiest route of N.F. Railways give a lot of advantage in increasing the line capacity of this section. A permanent speed restriction of 90 km per hour had also been removed in the process of this doubling. A three lane road over bridge of 60 m span with bow string girders has been constructed on National Highway 31-D which is a first on this Railway.

It is expected that with the completion of these two critical sections, trains to and from Northeast will be able to move at a much faster speed and thereby benefiting travelling public.

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.