Amazon's massive India bet! Andy Jassy announces $48 billion investment after meeting PM Modi | Taratala warehouse collapse: Death toll climbs to 8, five arrested as SIT launches probe | Oil prices crash, IndiGo takes off! Aviation and fuel stocks emerge as biggest winners | Passport is a travel document, not conclusive proof of citizenship: MEA | Kolkata: Taratala warehouse roof collapses | Indian Army's Trishakti Corps restores lifeline connectivity in North Bengal between Siliguri and Mirik | 19 million barrels flow through Strait of Hormuz, Trump declares oil prices are falling | No Hindi, no NEET: Vijay reignites Tamil Nadu's biggest political flashpoints | Messi creates World Cup history with record-breaking double; Mbappe equals Klose's mark hours later | Tech giant Oracle slashes 21,000 jobs while betting big on AI
Image credit: Free wallpaper

New production from KG D6 Project on track to start by mid-2020: Reliance

| @indiablooms | Feb 04, 2020, at 12:08 am

Mumbai/IBNS: The RIL-BP joint venture on Monday confirmed that it has completed the safe cessation of production in a planned manner, from the D1 D3 field in Block KG D6 (KG-DWN-98/3), off the east coast of India. The D1 D3 field was India’s first deepwater gas field to be put on production in April 2009.

The RIL-BP joint venture has successfully worked to extend the life of production from the D1 D3 Field which otherwise would have ceased production in 2015 due to issues of reservoir pressure and water ingress.

Through innovation and application of solutions, the field’s life was extended for almost five years, to Feb 2020, maximizing the recovery from the field.

The KG D6 Block has so far produced an overall 3 TCFe resulting in energy import savings of over USD 30 billion. These fields also established several global benchmarks in terms of operational performance including 99.9 % uptime and 100% incident-free operations.

As already informed, the JV has committed an additional $5 billion (Rs. 35,000 Crores) of investments towards monetizing about 3 TCFe (about 500 Million Barrels of Oil equivalent) reserves from three projects - R cluster, Satellite cluster and MJ fields. These projects will utilize the existing gas production infrastructure.

Further, this infrastructure can act as a hub for the development of any discovery from contiguous areas.

The first-gas from these fields is expected in mid-2020. The peak production from these three fields is expected to reach 1 BCFe per day which is about 15% of the then envisaged India’s demand.

Image credit: Free wallpaper


 

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.
Related Videos
RBI announces repo rate cut Jun 06, 2025, at 10:51 am
FM Nirmala Sitharaman presents Budget 2025 Feb 01, 2025, at 03:45 pm
Nirmala Sitharaman on Budget 2024 Jul 23, 2024, at 09:30 pm