Vijay-led TVK wins Tamil Nadu floor test as AIADMK split plays out | Congress veteran Sonia Gandhi admitted to Medanta Hospital in Gurugram | PM Modi halves convoy size after austerity call | Mulayam Singh's younger son Prateek Yadav dies at 38 | Protests erupt in Delhi after NEET UG 2026 cancellation over alleged paper leak | AIADMK cracks widen after Tamil Nadu defeat; faction backs Vijay-led TVK government | Himanta Biswa Sarma takes oath as Assam CM for second term after BJP’s landslide win | Bengali rights activist Garga Chatterjee arrested over alleged provocative remarks ahead of assembly polls | No return to full WFH yet: IT firms unlikely to change hybrid work model despite PM Modi’s appeal | Suvendu Adhikari Cabinet clears BSF land transfer, census rollout, Ayushman Bharat in Bengal
Bullet Train
First section of 21 km undersea tunnel of the Bullet train project opens in Maharashtra. Photo: PIB

Maharashtra: First section of 21 km undersea tunnel of the Bullet train project opens between Ghansoli and Shilphata

| @indiablooms | Jul 14, 2025, at 06:21 pm

The bullet train project has achieved a major milestone of opening the first section of the 21 km undersea tunnel between BKC and Thane.

The bullet train project recently achieved a major milestone by completing 310 km of viaduct construction.

Track laying, construction of overhead electrical wires, stations, and bridges is going on at a rapid pace. The construction work in Maharashtra has also picked up pace.

In parallel, the progress on procurement of systems for operations and control is also going on well.

Rolling Stock:  Japanese Shinkansen is currently running E5 trains. 

Next generation trains are E10.  In the spirit of strategic partnership between Japan and India, the Japanese government has agreed to introduce E10 Shinkansen trains in the Mumbai-Ahmedabad Bullet train project. 

It is noteworthy that E10 will be introduced simultaneously in India and Japan.

Japanese Technology: The entire 508 km corridor is being developed with Japanese Shinkansen technology.

It will set new benchmarks for speed, safety, and reliability. This reflects the deep strategic and technological cooperation between India and Japan.

Construction at Rapid Pace: Civil works are progressing at a rapid pace across the alignment.  310 km viaduct is constructed. 15 river bridges are completed and 4 are in the advanced stages of construction.

Out of 12 stations, 5 are completed and 3 more are now reaching completion stage. The station at BKC is an engineering marvel.

The station will be located 32.5 m below ground and the foundation is designed to support the construction of a 95 m high building above ground.

Future Corridors in Pipeline: The success of the Mumbai-Ahmedabad High-Speed Rail (MAHSR) project is laying the foundation for future bullet train corridors in India. Future corridors are also under active consideration.

This remarkable pace of development showcases India’s capability to execute world-class infrastructure using cutting-edge global technology, with Japan playing a pivotal role as a trusted partner in this transformative journey.

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.